Swimming Pool Permit Cost in Round Rock, TX (2026)
Residential swimming pool permit fees for the City of Round Rock, Texas (Williamson County, Austin metro), pulled directly from the Building Inspection Division's official department fee pages. Round Rock prices an in-ground swimming pool at a flat $350.00 building permit, and a spa, hot tub, or above-ground pool at a flat $125.00 - the same at any size, because each is a single flat line. Plan review is bundled into the permit fee, and Texas has no statewide levy. One source-currency note up front: the live fee pages carry no printed effective date (they reference the current 2024 codes), and the only dated companion PDF is marked "Updated August 2023" - confirm current rates with the Building Inspection Division at 512-218-5428 before budgeting.
This guide covers: The City of Round Rock residential swimming pool building permit fee as published on the Building Inspection Division's department fee pages - a flat $350.00 for an in-ground pool and a flat $125.00 for a spa, hot tub, or above-ground pool. Plan review is bundled into the permit fee (the department states "no additional fees will be added to the permit fee").
Important note on source currency: the live Round Rock fee pages carry no printed effective date. They reference the current 2024 codes, so the content is current, but the only dated companion document (the Planning and Development Fees Summary PDF) is marked "Updated August 2023" - more than 24 months old. Confirm the current pool fee with the department at 512-218-5428 before relying on any figure for a load-bearing budget.
This guide does NOT cover: pool construction and equipment cost, the required pool electrical bonding (a separate standalone trade permit, flat $50), a required safety-barrier fence, water/sewer or impact fees, or HOA approvals. These are separate and are not included in the pool building permit fee.
A residential in-ground swimming pool permit in Round Rock, TX is a flat $350.00, and a spa, hot tub, or above-ground pool is a flat $125.00 - the same at any size, because each is a flat line. Plan review is bundled in, and the required pool electrical bonding is a separate $50.00 trade permit. Texas adds no state levy. These figures come from the department's live fee pages, which carry no printed effective date (the only dated companion PDF is "Updated August 2023"), so confirm current rates with the Building Inspection Division at 512-218-5428 before filing.
- Round Rock charges a flat $350.00 for an in-ground swimming pool building permit - the same regardless of pool size, because it is a single flat line, not a valuation-based fee.
- A spa, hot tub, or above-ground pool is a flat $125.00 - a much lower tier than the in-ground pool.
- Plan review is bundled into the permit fee; the department states no additional fees are added to it. The required pool electrical bonding is a separate standalone trade permit at a flat $50.00.
- Source-currency caveat: the live fee pages carry no printed effective date (they reference the current 2024 codes), and the only dated companion PDF is "Updated August 2023" (more than 24 months old). Confirm the current pool fee with the Building Inspection Division at 512-218-5428 before filing.
- Among verified Texas cities, Round Rock's $350 in-ground pool permit sits at the high end - above Irving's $240 and Arlington's $275, and tied with Pearland's $350.
- Texas has no statewide percentage permit levy - unlike Virginia's 2% USBC add-on - so the flat figure is the whole pool building permit (plus the separate $50 electrical bonding permit).
Round Rock Pool Permit Fee Structure
The residential pool permit is a flat fee by type, priced the same regardless of pool size, with plan review bundled in. Pool electrical bonding is a separate standalone trade permit. There is no statewide levy. All figures are from the Building Inspection Division's live department fee pages; the live pages carry no printed effective date, and the only dated companion PDF is "Updated August 2023" - confirm current rates before relying on them.
| Item | Fee | How It Is Calculated |
|---|---|---|
| In-ground swimming pool building permit | $350.00 | Flat line - same at any pool size; plan review bundled in. |
| Spa, hot tub, or above-ground pool | $125.00 | Flat line - a lower tier than an in-ground pool. |
| Pool electrical bonding | $50.00 | Separate standalone electrical trade permit; not part of the pool building line. |
| Plan review | Bundled | Included in the permit fee; department states no additional fees are added. |
| Work-before-permit penalty | Double fee | Starting work before the permit is issued doubles the permit fee. |
| State percentage levy | None | Texas has no statewide permit levy. |
Source: City of Round Rock Building Inspection Division department fee pages (retrieved June 10, 2026). The $350 in-ground and $125 above-ground/spa figures are exact on the live pages, but those pages carry no printed effective date and the only dated companion PDF is "Updated August 2023." Pool electrical bonding is a separate $50 trade permit. Confirm current rates with the Building Inspection Division at 512-218-5428 before filing.
Worked Examples - Real Pool Projects in Round Rock
Because the pool permit is a flat fee by type, the building-permit cost does not change with pool size. The examples below use the department's published amounts; confirm currency before budgeting.
A homeowner builds a standard in-ground gunite pool in the backyard.
- In-ground pool building permit: $350.00
- Pool electrical bonding (separate): $50.00
- Typical combined: $400.00 (two separate permits)
The $400 is two separate permits, not a merged fee. Plan review is bundled into the $350 building permit. The same $350 applies whether the pool is small or large.
A homeowner sets an above-ground pool or a hot tub / spa.
- Above-ground pool / spa / hot tub permit: $125.00
- Electrical, if wired (separate trade permit): $50.00
- Building permit: $125.00
A spa, hot tub, or above-ground pool is the lower $125 tier. If it is hard-wired, the electrical is a separate $50 trade permit.
A contractor begins excavation before the pool permit is issued.
- In-ground pool building permit: $350.00
- Work-before-permit penalty: × 2
- Doubled permit fee: $700.00
Round Rock doubles the permit fee when work begins before a permit is issued. Pull the permit first to avoid the penalty.
When This Estimate May Not Apply
The flat $350 in-ground / $125 above-ground figures come from Round Rock's live department fee pages. Route your project to the Building Inspection Division before relying on this figure if any of the following applies:
- The rates may have changed. The live fee pages carry no printed effective date and the only dated companion PDF is "Updated August 2023" - confirm the current pool fee at 512-218-5428 before budgeting.
- You have not accounted for the pool electrical. Pool electrical bonding is a separate standalone trade permit ($50), not part of the pool building permit.
- A safety-barrier fence is required. Pool enclosure/barrier requirements are handled separately from the pool building permit.
- Work started before the permit issued. Round Rock doubles the permit fee for work-before-permit.
- Impact, water/sewer, or utility fees apply. These are billed separately from the pool building permit.
- HOA or deed-restriction rules apply. Placement and approval rules are handled separately from the flat permit fee.
The source-currency caveat, separate pool electrical, safety-barrier requirements, the work-before-permit penalty, utility/impact fees, and HOA rules are all excluded from or may change the pool building permit figures on this page, and the page-standard disclaimer applies - always verify with the Round Rock Building Inspection Division before budgeting.
Round Rock Pool Permit Cost vs Other Verified Texas Cities
Texas cities mostly price residential in-ground pool permits as a flat building-permit line, but the amounts range widely. The table below compares Round Rock's flat in-ground pool line with other verified Texas cities. Each is the pool building permit only; separate electrical/bonding permits are extra where they apply.
| City | Pool Fee Basis | In-Ground Pool Permit |
|---|---|---|
| Irving, TX | Flat line | $240.00 |
| Killeen, TX | Flat line | $245.00 |
| Arlington, TX | Flat line | $275.00 |
| Plano, TX | Flat line | $300.00 |
| Round Rock, TX | Flat line | $350.00 |
| Pearland, TX | Flat line | $350.00 |
Scope note: Round Rock's $350.00 in-ground pool permit is at the high end among verified Texas cities - above Irving's $240, Killeen's $245, Arlington's $275 and Plano's $300, and tied with Pearland's $350. All are flat pool building-permit lines; pool electrical/bonding is a separate permit where it applies. Round Rock's figure is from live pages with no printed effective date - confirm currency.
See Round Rock's full residential fee schedule, or compare another verified Texas city.
Frequently Asked Questions
Who to Contact
| Department | City of Round Rock - Planning and Development Services, Building Inspection Division |
| Phone | 512-218-5428 |
| Location | 301 W. Bagdad Avenue, Suite 210, Round Rock, TX 78664 (Williamson County, Austin metro) |
| Fee pages | Round Rock Building Inspection Division fee pages |
Sources
-
City of Round Rock - Building Inspection Division fee pages City of Round Rock official department fee pages (retrieved via browser June 10, 2026). Primary source for the $350 in-ground pool, $125 above-ground/spa, $50 standalone trade permit, and bundled plan review. Live pages carry no printed effective date; the only dated companion PDF is "Updated August 2023." verify currency
-
Texas Local Government Code, Chapter 214 Texas statute (.gov) confirming municipal building-regulation authority and that Texas imposes no statewide percentage building-permit levy. Context for the "no statewide levy" statement. Verified September 2026.