Skip to main content

Pool Permit Cost in Pearland, TX (2026)

Residential swimming pool permit fees for the City of Pearland, Texas, pulled directly from the city Building Permit Fee Schedule (Exhibit B). Pearland prices a swimming pool building permit as a flat $350.00 - the same at any pool size or value, because it is a single flat line, not a valuation-based fee. Pool electrical and pool plumbing are each a separate $120.00 trade permit. The schedule also states a residential building plan-review fee equal to one-half of the building permit fee; whether that clause attaches to a flat pool line is not stated, so this guide does not fold it into the headline. Texas has no statewide permit levy, and Pearland adds no percentage surcharge.

Swimming Pool Permit
$350.00 flat
Fee Basis
Flat - not valuation-based
Pool Electrical / Plumbing
$120.00 each - separate
Plan Review on Pool
Not stated - confirm with city
State / City Percentage Levy
None (Texas has no state levy)
Fee Status
Live schedule - no printed effective date, verify current
What This Guide Covers - and What It Does Not

This guide covers: The City of Pearland (Brazoria, Harris, and Fort Bend Counties) residential swimming pool permit fee as printed on the city Building Permit Fee Schedule (Exhibit B) - a flat $350.00 swimming pool building permit. That figure is exact from the schedule and is the same whether the pool is a small plunge pool or a large in-ground pool, because it is a single flat line rather than a valuation-based fee.

Pool electrical and plumbing are separate: the $350.00 figure is the building permit for the pool. Pool electrical and pool plumbing are each pulled as a separate residential trade permit at $120.00 each on Pearland's schedule. A pool with both a bonding/electrical permit and a plumbing permit would add $240.00 to the $350.00 building permit.

On the plan-review clause: Pearland's schedule prints "Plan Review: an amount equal to one-half of the building permit fee" under residential building permits. The schedule does not state whether this applies to a flat pool line (which is not a per-square-foot building permit). This guide does not assume it applies and does not add it to the headline; if it did apply it could add up to $175.00. Confirm with Community Development before budgeting.

Important note on fee schedule age: The city's live fee page prints no effective date or adopting ordinance for the building exhibit. Treat $350.00 as the current published amount and confirm it with Pearland Community Development at (281) 652-1600 before relying on any number.

This guide does NOT cover: pool construction cost, water/wastewater impact fees, parkland or tree-mitigation fees, gas-line permitting for a pool heater, a pool safety barrier or fence, HOA approvals, or zoning setback questions. These are separate schedules and are not included in the $350.00.

Key Takeaways
  • Pearland charges a flat $350.00 for a swimming pool building permit - the same fee regardless of pool size or construction value, because it is a single flat line, not a valuation-based schedule.
  • Pool electrical and pool plumbing are each a separate $120.00 residential trade permit. They are not included in the $350.00 pool building permit; both together would add $240.00.
  • The schedule prints a residential plan-review fee of one-half the building permit fee, but does not state that it applies to a flat pool line - so this guide does not add it. If it applied, it could add up to $175.00. Confirm with Community Development.
  • Texas has no statewide percentage permit levy - unlike Virginia's 2% USBC add-on - and Pearland adds no city percentage surcharge on the pool permit.
  • For context among verified Texas cities: Pearland's $350.00 pool building permit is one of the highest on the site - close to Denton's $357 and above Longview's $305, though below League City's $600 - and each city bundles or excludes trades differently.
  • The figures come from the current City of Pearland Building Permit Fee Schedule (Exhibit B), which prints no effective date. Confirm current amounts with Community Development at (281) 652-1600 before budgeting.

Pearland Pool Permit Fee Structure

The pool building permit is a single flat line, priced the same regardless of pool size or value. Pool electrical and pool plumbing are separate $120.00 trade permits. There is no valuation calculation on the pool line, no technology surcharge, and no statewide levy.

Item Fee How It Is Calculated
Swimming pool building permit $350.00 Flat fee from the "Swimming pool" residential line - same at any pool size or value.
Pool electrical $120.00 Separate residential trade permit (pool electrical/plumbing line) - not part of the pool fee.
Pool plumbing $120.00 Separate residential trade permit - not part of the pool fee.
Plan review on a flat pool line Not stated The "half of building permit fee" clause is printed for building permits; the schedule does not state it applies to a flat pool line.
State / city percentage levy None Texas has no statewide permit levy; Pearland adds no percentage surcharge.

Source: City of Pearland Building Permit Fee Schedule (Exhibit B) plus the Electrical/Plumbing trade schedules. The schedule prints no effective date. The plan-review row is shown to disclose an unresolved question, not to add a fee - confirm plan-review treatment for a pool with Community Development.

Worked Examples - Real Pool Projects in Pearland

Because the pool building permit is a flat fee, the permit cost does not change with pool size or value. What adds to the total is the separate electrical and plumbing trade permits. Figures are from the city Building Permit Fee Schedule (Exhibit B).

Example 1: In-ground pool, building permit only

A homeowner pulls only the pool building permit; the pool contractor handles trade permits separately or none is required at filing.

  • Swimming pool building permit: $350.00
  • Texas state levy: $0.00 (none)
  • Pool building permit: $350.00 (before trades)

The same $350.00 applies whether the pool is small or large - it is a flat line, not valuation-based. Confirm whether plan review attaches to the pool line with Community Development.

Example 2: Pool with electrical and plumbing trade permits

A new in-ground pool whose bonding/electrical and equipment plumbing are each pulled as separate residential trade permits.

  • Swimming pool building permit: $350.00
  • Pool electrical trade permit: $120.00
  • Pool plumbing trade permit: $120.00
  • Pool + trades: $590.00

Whether both trade permits are required depends on your pool's scope. This figure excludes any plan-review charge, which the schedule does not state applies to a pool line. Confirm with Community Development.

Example 3: Comparing pool size does not change the building fee

Two homeowners, one building a small pool and one building a large pool, each pulling the building permit only.

  • Small pool - building permit: $350.00
  • Large pool - building permit: $350.00
  • Same building permit either way: $350.00

The flat line means the pool building permit cost is identical regardless of size or value. Only the separate trade permits would differ. Confirm current fees with Community Development.

When This Estimate May Not Apply

The flat $350.00 covers the pool building permit itself on Pearland's Exhibit B schedule. Route your project to Pearland Community Development at (281) 652-1600 before relying on this figure if any of the following applies:

  • Pool electrical and plumbing are permitted separately. Each is a $120.00 residential trade permit, not included in the $350.00 pool building permit.
  • Plan review may apply. The schedule prints a residential plan-review fee equal to half the building permit fee, but does not state it applies to a flat pool line. If it did, it could add up to $175.00 - confirm with Community Development.
  • Your pool needs a safety barrier. Texas requires a compliant barrier around a residential pool. Whether Pearland permits the barrier separately is a department determination; this guide does not assume a barrier fee.
  • Your pool has a gas heater. Gas-line work may be permitted as a separate trade permit - a question for the department.
  • Impact or utility fees apply. Water/wastewater impact, parkland, and tree-mitigation fees are on separate schedules and are not part of the pool permit.
  • The schedule is updated. The figures come from the live fee schedule with no printed effective date and can change by ordinance - confirm before filing.

Pool electrical, plumbing, plan review, barrier, gas-heater, and impact fees are excluded from the pool building permit on this page, and the page-standard disclaimer applies - always verify with Pearland Community Development before budgeting.

Pearland Pool Permit Cost vs Other Verified Texas Cities

Texas cities price pool permits on different models - flat building permits, valuation-based fees, and flat fees that bundle trades. The table below compares Pearland's flat pool building permit with other verified Texas cities. Scope differs, so each figure notes its basis.

City Pool Fee Basis Pool Building Permit
Pearland, TX Flat pool line; trades separate ($120 ea) $350.00
League City, TX Flat pool line; trades separate $600.00
Denton, TX Flat pool line; electrical separate $357.00
Longview, TX Flat building permit; electrical separate $305.00

Scope note: Pearland's $350.00 is a flat pool line with pool electrical and plumbing ($120 each) separate. League City's $600, Denton's $357, and Longview's $305 are all flat pool lines with trades billed separately. Pearland sits at the higher end of the verified Texas set - just below Denton and above Longview. Confirm current figures and trade treatment with each department.

Next Step

See Pearland's full residential fee schedule, or compare a nearby Houston-area city.

Frequently Asked Questions

A swimming pool building permit is a flat $350.00 - the same at any pool size or value. Pool electrical and pool plumbing are each a separate $120.00 trade permit. A residential plan-review clause (half of the building permit fee) is printed on the schedule but not stated to attach to a flat pool line, so it is not added here. Texas adds no state levy. Figures are from the city Building Permit Fee Schedule (Exhibit B), which prints no effective date.
No. Pearland's $350.00 pool building permit is a flat line - the same whether the pool is small or large, and not tied to construction value. Only the separate trade permits (electrical and plumbing, $120 each) would change the all-in total.
No. The $350.00 is the building permit. Pool electrical and pool plumbing are each a separate $120.00 residential trade permit on Pearland's schedule. A pool with both would add $240.00 to the $350.00. Confirm with Community Development which trade permits your pool requires.
The schedule prints a residential plan-review fee equal to one-half of the building permit fee, but it does not say whether that applies to a flat pool line (which is not a per-square-foot building permit). This guide does not assume it applies and does not add it to the $350.00. If it did apply, it could add up to $175.00. Confirm plan-review treatment for a pool with Community Development.
Texas requires a compliant safety barrier around a residential pool. Whether Pearland pulls the barrier as its own permit or folds it into the pool permit is a determination for Community Development. This guide does not assume a barrier fee.
Pearland's $350.00 pool building permit is at the higher end for verified Texas cities - just below Denton's $357 and above Longview's $305, though below League City's $600. All of these bill pool trades separately, so add each city's electrical and plumbing permits before comparing all-in totals.

Who to Contact

Department City of Pearland - Community Development (Permits)
Phone (281) 652-1600
Location City of Pearland, Brazoria / Harris / Fort Bend Counties, Texas
Fee schedule City of Pearland Permits & Development Fees

Sources

Official Sources - Recorded July 2026
  • City of Pearland - Permits & Development Fees (Building Permit Fee Schedule, Exhibit B) Pearland, TX (.gov) - the city's official Permits & Development Fees page. Primary source for the $350.00 swimming pool building permit, the $120.00 pool electrical/plumbing trade permits, and the one-half plan-review clause. Read live July 4, 2026 live schedule - no printed date, verify current
  • Texas Local Government Code, Chapter 214 Texas statute (.gov) confirming municipal building-regulation authority and that Texas imposes no statewide percentage building-permit levy. Context for the "no statewide levy" statement. Verified July 2026.
Always verify current pool permit fees directly with City of Pearland Community Development before budgeting or filing. The figures on this page come from the city Building Permit Fee Schedule (Exhibit B), which prints no effective date. The $350.00 is the pool building permit; pool electrical and plumbing ($120.00 each) are separate, and any plan-review treatment for a pool is unconfirmed. Call (281) 652-1600 to confirm your project's full fees before submitting an application.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by City of Pearland Community Development at the time of application. The $350.00 swimming pool building permit shown is exact from the city Building Permit Fee Schedule (Exhibit B), which prints no effective date. Pool electrical and plumbing, any plan-review charge, a safety barrier, gas-heater permitting, impact and utility fees, construction costs, zoning setbacks, and HOA approvals are excluded from the pool building-permit figure on this page. Verify all fees directly with the department before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.