Building Permit Fee Calculator (2026)

Permit Fee Calculator
Actual formulas from official .gov fee schedules

Live coverage: selected Virginia jurisdictions and Washington, DC. Project options update by jurisdiction - only fee types supported by the official schedule appear. Square-foot and tiered projects (decks in Norfolk, additions in Virginia Beach, DC alteration tiers, new construction) are documented on each jurisdiction page.

Building Permit Package · Fairfax County, VA · $15,000 Deck
$688.50
  • Building Permit Fee $450.00
  • Plan Review (50%) $225.00
  • Virginia State Levy (2%) $13.50

Formula: max(cost × 3%, $72) + 50% plan review + 2% VA levy on subtotal. Estimate only - verify with Fairfax County Land Development Services before filing.

Source effective 2024-07-01
Last verified 2026-03-15
Jurisdiction page Verification details
What this estimate excludes
  • Trade permits (electrical, plumbing, mechanical/HVAC) - issued separately with their own fees.
  • Zoning review, site plan review, or land-disturbance review charged outside the building permit.
  • Impact fees, proffer fees, school/transportation impact charges where the jurisdiction collects them.
  • Utility connection or tap fees (water, sewer, gas, electric meter connection).
  • Re-inspection fees, after-hours inspection fees, revision fees, and work-without-permit penalty fees.
  • Final fees are determined by the local building department at permit issuance and may differ from this estimate.

PermitPrice is not an official quotation. See Disclaimer and Methodology.

Verify with the building department
Fairfax County - Land Development Services
Fee schedule: Official document
Full breakdown: Jurisdiction page

This calculator covers the building permit fee only. Trade permits (electrical, plumbing, HVAC) are separate and issued at additional cost. Always verify with your local building department before filing.

Don't see your jurisdiction? Email contact@permitprice.com with the jurisdiction name, state, project type, and a link to the official fee schedule (if you have one). Requests with a working .gov source move up the queue. See Coverage and the source library.
Fairfax County full breakdown Visualize cost stack (Fairfax addition) All Virginia jurisdictions

How This Is Calculated

Every supported jurisdiction-and-project combination uses the actual formula from the adopted fee schedule. No generic ranges or averages. Square-foot and tiered project types not yet wired into the widget (Virginia Beach decks/additions, Norfolk decks, DC alteration tiers) are routed to the matching jurisdiction page where the same official formula is shown with worked examples.

Step Fee Component Formula (Fairfax County) Source
1 Building Permit Fee max(project cost × 3%, $72 min) Appendix Q, Chapter 61 (FY2025)
2 Plan Review Fee Building permit fee × 50% Appendix Q, Chapter 61 (FY2025)
3 Virginia USBC State Levy (Step 1 + Step 2) × 2% Code of Virginia §36-139
4 Total Step 1 + Step 2 + Step 3 -

Pool exception: In-ground pools in Fairfax County use a flat $270 permit fee (not the 3% formula). Plan review adds 50% ($135). State levy adds 2% on the combined $405. Total pool permit: $413.10.

Data Sources for This Calculator

What This Calculator Shows That Others Don't

Real-World Example: $15,000 Deck, Fairfax County VA

400 sqft composite deck, attached to dwelling · Building permit (residential alteration) · Stated valuation: $15,000 · Formula: Appendix Q FY2025 (effective July 1, 2024)

Building Permit Fee (max(3% × $15,000, $72)) $450.00
Plan Review Fee ($450 × 50%) $225.00
Virginia USBC State Levy ($675 × 2%) $13.50
Total Building Permit Fees $688.50

What generic cost guides say for this same project: $300-$500. The actual number is $688.50 - 37-130% higher than the generic estimate, depending on which guide you consult.

When This Calculator's Results Don't Apply

  • Unsupported jurisdictions: This calculator covers 7 Virginia jurisdictions plus Washington, DC. Each one uses its own official fee formula loaded from its source.json. For other jurisdictions (Prince William County, Arlington County, Alexandria City, etc.), use the matching jurisdiction page or the request-jurisdiction CTA above.
  • Square-foot and tier-formula projects: Norfolk decks, Virginia Beach decks and additions, and DC alteration tiers are routed to the matching jurisdiction page where the same official formula is shown with worked examples. Those project-and-jurisdiction combinations do not appear in the dropdown.
  • Trade permits: Electrical, plumbing, and HVAC permits are not included. In Fairfax County, a 200-amp electrical service change adds $341-$633 separately.
  • New residential construction: Per-square-foot rates for new homes and new garages are not wired into the dropdown for every jurisdiction. Use the matching jurisdiction page for those calculations.
  • After annual rate changes: Virginia jurisdictions typically update their fee schedules each July 1; DC updates outside that cycle. Re-verification dates are shown on each jurisdiction page. If the current date is past the next verification date, confirm against the latest official fee schedule.
  • When stated valuation is disputed: If the building official determines your stated construction value is below market, they may substitute the ICC Building Valuation Data table, increasing the base fee.

Calculator FAQ

Because those three charges appear as separate line items on your actual permit invoice. The building permit fee, plan review fee, and Virginia USBC state levy are collected for different purposes and may even go to different entities (the state levy is remitted to the Virginia DHCD). Showing them separately lets you verify each number against the official fee schedule rather than just trusting a black-box total.
No. This calculator covers the building permit fee only. In Virginia, electrical, plumbing, and HVAC (mechanical) permits are issued as separate trade permits with their own fee schedules. In Fairfax County, for example, an electrical service change permit runs $341-$633 depending on amperage - that's on top of the building permit shown here. If your project includes any trade work, budget for those additional permit fees separately.
For Fairfax County residential alterations and in-ground pools, the formula is taken directly from Appendix Q of the Land Development Services fee schedule (FY2025, effective July 1, 2024), verified on March 15, 2026. If your stated construction value matches what the building official uses, this estimate matches the actual permit invoice. The main exception: if the official disputes your stated value and substitutes ICC Building Valuation Data, the base fee will be higher. Always verify before filing.
Yes. PermitPrice schedules source re-verification for each jurisdiction before the annual July 1 rate change. Fairfax County's next verification is due by July 15, 2026. When new Appendix Q values are confirmed, the calculator formula is updated. Until then, fees reflect Appendix Q FY2025.
Next Step

See the full formula for your jurisdiction - including all fee components, project-type breakdowns, worked examples, and permit office contact info.

Always verify current fees directly with your local building department before budgeting or filing. Fee schedules change annually. Fairfax County Land Development Services: (703) 222-0801 or fairfaxcounty.gov/landdevelopment.
Disclaimer: All fee estimates from this calculator are for informational purposes only and are not official permit quotations. Actual permit fees are determined by the applicable building department at the time of permit application. Fees, surcharge rates, and requirements can change without notice. Verify all fees directly with the relevant building department before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.