Pool Permit Cost in New Braunfels, TX (2026)

Residential swimming pool permit fees for the City of New Braunfels, Texas (Comal and Guadalupe Counties), pulled from the Code of Ordinances, Appendix D - Fee Schedule. New Braunfels is one of the few Texas cities where a genuine all-in pool figure can be reproduced from the adopted code, because the ordinance prints every component: an in-ground pool is a flat $200.00 and an above-ground pool is $100.00 under Building Permit Fee Schedule A Residential, each then carrying a $35.00 residential inspection fee and a 3% technology fee, with the result rounded down to the whole dollar. That works out to $242.00 for an in-ground pool and $139.00 for an above-ground pool. Pool electrical stays separate: the electrical schedule prints a $12.50 swimming pool circuit plus a $15.00 issuance fee.

In-Ground Pool, All-In
$242.00 (with inspection + 3% tech)
Above-Ground Pool, All-In
$139.00 (with inspection + 3% tech)
Base Permit Fees
$200.00 in ground / $100.00 above ground
Add-Ons Applied
$35.00 inspection + 3% technology fee
Pool Electrical
$12.50 pool circuit + $15.00 issuance - separate
Fee Status
Source age warning - last amended October 9, 2023, verify current
What This Guide Covers - and What It Does Not

This guide covers: the City of New Braunfels residential swimming pool permit fees as codified in Appendix D, Sec. B(a) "Building Permit Fee Schedule A Residential" - "Pool = Above Ground $100.00 / In Ground $200.00" - together with the Sec. A add-ons that stack on a residential job: the $35.00 residential inspection fee and the 3% information-technology fee. All four inputs are exact printed figures, and the $242.00 and $139.00 totals are arithmetic on them.

How the $242.00 is built: $200.00 in-ground pool + $35.00 inspection = $235.00, then $235.00 × 1.03 = $242.05 for the 3% technology fee, then the ordinance's round-down-to-the-whole-dollar rule at Sec. B(k) gives $242.00. The above-ground path is $100.00 + $35.00 = $135.00, × 1.03 = $139.05, rounded down to $139.00. Every step is reproducible from the printed code.

What this guide deliberately does NOT add: Appendix D also prints a $50.00 permit application fee and a residential plan review fee of 25% of permit cost, but both are printed as applying to "all new construction, additions and substantial alterations". Whether a standalone pool falls in that bucket is a Building Division determination, and the ordinance does not say. This page therefore excludes both from the $242.00 rather than guessing. If the department does apply them, your cost would be materially higher - ask before you file.

Source age - read this first: Appendix D carries no printed effective date of its own. Its amendment history for the building-permitting section ends at Ord. No. 2023-76, Sec. 4, adopted October 9, 2023 - roughly 33 months before the July 2026 extraction, past our 24-month currency threshold. The Municode page itself is labelled current (version May 28, 2026). A city newsflash also confirms Council amended development-related fees effective April 1, 2024. Treat these as the codified figures and confirm current amounts with the Building Division.

This guide does NOT cover: water, wastewater and roadway impact fees (Chapter 100 and utility ordinances, outside Appendix D), Comal County and Guadalupe County fees, New Braunfels Utilities connection charges, pool barrier or enclosure fencing as a pool-specific item, pool construction cost, HOA approvals, or zoning setbacks.

Key Takeaways
  • New Braunfels is unusual among Texas cities in that a real all-in pool figure can be reproduced from the adopted code: $242.00 in-ground and $139.00 above-ground, both derived step by step from printed ordinance components rather than estimated.
  • The base fees are $200.00 in-ground and $100.00 above-ground under Appendix D, Sec. B(a). Both are flat - pool size, water surface area and construction value do not change them.
  • Two add-ons stack on every residential job: a $35.00 residential inspection fee and a 3% information-technology fee. On an in-ground pool that is $235.00 × 1.03 = $242.05, rounded down under the ordinance's whole-dollar rule to $242.00.
  • The $50.00 application fee and the 25%-of-permit-cost plan review are printed for "new construction, additions and substantial alterations" only. Whether a standalone pool counts is a Building Division call, so neither is folded into the $242.00 here. If both applied, the cost would rise substantially.
  • Pool electrical is priced separately and cheaply compared with peer cities: the electrical schedule prints a $12.50 swimming pool circuit plus a $15.00 issuance fee, versus a $70.00 electrical minimum in Beaumont and a $59.00 base in League City.
  • Peer context: New Braunfels' $242.00 all-in sits between Brownsville's $200.00 flat line and Beaumont's $275.00, and far below League City's $600.00. But note that the $242.00 already includes inspection and technology charges the others do not - compare the basis, not just the number.
  • Source-age caution: the building-permitting section was last amended by Ord. No. 2023-76 on October 9, 2023, roughly 33 months before extraction and past our 24-month threshold. A separate city newsflash confirms development-related fee amendments effective April 1, 2024. Confirm current amounts with the Building Division.

New Braunfels Pool Permit Fee Structure

Every row below is a printed component of Appendix D. The pool line itself is flat; the inspection fee and technology fee are the two add-ons that make the all-in figure reproducible. Rows where the ordinance is silent say so rather than assuming a number.

Item Fee How It Is Calculated
Pool, in ground $200.00 Verified flat fee, Appendix D Sec. B(a) Schedule A Residential - same at any pool size or value.
Pool, above ground $100.00 Verified flat fee from the same table. Half the in-ground rate.
Residential inspection fee $35.00 Appendix D, Sec. A. Re-inspections are $35.00 and double for each subsequent re-inspection.
Information technology fee 3% Appendix D, Sec. A - 3% on all review, building, zoning and development related fees.
Round-down rule To the whole dollar Sec. B(k). $242.05 becomes $242.00; $139.05 becomes $139.00.
In-ground pool, all-in $242.00 ($200.00 + $35.00) × 1.03 = $242.05, rounded down. Excludes pool electrical.
Above-ground pool, all-in $139.00 ($100.00 + $35.00) × 1.03 = $139.05, rounded down. Excludes pool electrical.
Pool electrical $12.50 circuit + $15.00 issuance Electrical schedule - a swimming pool circuit is $12.50, plus the $15.00 issuance fee. Separate permit.
Application fee and plan review $50.00 + 25% - applicability to pools unstated Printed for "new construction, additions and substantial alterations". The ordinance does not say whether a standalone pool qualifies, so neither is added here.
State / city percentage levy None (beyond the 3% tech fee) Texas has no statewide permit levy. The 3% is a city information-technology fee, not a state charge.

Source: City of New Braunfels Code of Ordinances, Appendix D - Fee Schedule (Sec. A. Schedule of fees; Sec. B. Additional fees specific to building permitting), as codified on the Municode code library. Amendment history for the building-permitting section ends at Ord. No. 2023-76, Sec. 4, October 9, 2023. Note: an older "2018 Fees" PDF is still linked from the city's Building Permits page; it is a superseded printing of Appendix D with a valuation-tiered residential table and was not used for any figure here.

Worked Examples - Real Pool Projects in New Braunfels

Every figure below is arithmetic on printed components of Appendix D. Each example states which add-ons it applied and which it did not, so the assumptions are visible rather than buried.

Example 1: In-ground gunite pool, 450 sq ft of water surface

The standard New Braunfels backyard pool. The permit line is flat, so the surface area does not enter the calculation.

  • Pool, in ground: $200.00 (verified flat)
  • Residential inspection fee: $35.00 (verified flat)
  • Subtotal: $235.00
  • 3% technology fee: $7.05 ($235.00 × 0.03)
  • Round down to the whole dollar (Sec. B(k)): $242.05 → $242.00
  • Verified all-in pool permit: $242.00

Every input is a printed ordinance figure and every step is reproducible. The $50.00 application fee and 25% plan review are not added because the ordinance prints them for new construction, additions and substantial alterations, and does not say whether a standalone pool qualifies. Pool electrical is separate.

Example 2: Above-ground pool

The same add-on path applied to the cheaper base line.

  • Pool, above ground: $100.00 (verified flat)
  • Residential inspection fee: $35.00 (verified flat)
  • Subtotal: $135.00
  • 3% technology fee: $4.05 ($135.00 × 0.03)
  • Round down to the whole dollar: $139.05 → $139.00
  • Verified all-in pool permit: $139.00

Choosing above-ground over in-ground saves $103.00 on the permit ($242.00 - $139.00). Note the $35.00 inspection fee is the same either way, so the saving is smaller in percentage terms than the base-fee difference alone suggests.

Example 3: In-ground pool including the pool electrical circuit

Pool equipment needs a dedicated circuit. New Braunfels prices that on the electrical schedule, separately from the building permit.

  • All-in pool building permit: $242.00 (from Example 1)
  • Swimming pool circuit: $12.50 (verified, electrical schedule)
  • Electrical issuance fee: $15.00 (verified)
  • Verified total, single-circuit pool: $269.50

$242.00 + $12.50 + $15.00 = $269.50, on the stated assumption of a single pool circuit. A pool needing additional circuits, a panel change or a meter upgrade will draw more electrical line items - the electrical schedule prices additional circuits at $10.00 each and residential panels from $20.00 to $65.00 by circuit count.

Example 4: Pool permit if the department applies the application fee and plan review

The scenario this page does not publish as the headline number, shown explicitly so the open question is visible rather than hidden. This applies only if the Building Division classifies a pool as new construction, an addition or a substantial alteration.

  • Pool, in ground: $200.00 (verified flat)
  • Permit application fee, residential: $50.00 (verified - applicability to pools unstated)
  • Plan review at 25% of permit cost: $50.00 ($200.00 × 0.25 - applicability unstated)
  • Residential inspection fee: $35.00
  • Subtotal: $335.00; 3% technology fee: $10.05
  • Conditional figure, not the published answer: $345.00

$345.05 rounded down to $345.00. This is a conditional scenario, clearly labelled - it is what the permit would cost if those two lines are applied to a standalone pool. The ordinance does not state that they are, which is why $242.00 is the figure published on this page. Ask the Building Division which classification your pool receives.

When This Estimate May Not Apply

The $242.00 all-in figure covers the in-ground pool permit, the residential inspection fee and the 3% technology fee under the codified Appendix D. Route your project to the City of New Braunfels Building Division before relying on it if any of the following applies:

  • The department applies the $50.00 application fee and the 25% plan review. This is the largest open question on the page. Both are printed for "new construction, additions and substantial alterations", and the ordinance does not say whether a standalone pool qualifies. If both apply, the figure becomes $345.00 as shown in Example 4.
  • The fee schedule has been amended since October 9, 2023. The building-permitting section's amendment history ends there, roughly 33 months before extraction and past our 24-month threshold. A city newsflash confirms Council amended development-related fees effective April 1, 2024, so the counter amount may differ from the codified figure.
  • Your pool needs more than a single electrical circuit. The $269.50 in Example 3 assumes one $12.50 swimming pool circuit plus the $15.00 issuance fee. Additional circuits are $10.00 each and a panel change runs $20.00 to $65.00 by circuit count.
  • Your pool has gas-fired heating or dedicated plumbing. Those draw separate trade permits under the same appendix and are not in the $242.00.
  • A pool barrier or enclosure is required. Texas requires a compliant residential pool barrier. Appendix D prints a general "Fence - $50.00" residential line but no pool-barrier line item, so how a barrier is permitted for a pool is a department question. No pool-barrier figure is invented here.
  • Impact or utility fees apply. Water, wastewater and roadway impact fees are set outside Appendix D (Chapter 100 Roadway Impact Fees and utility ordinances). New Braunfels Utilities connection charges, and Comal or Guadalupe County fees, are also separate.
  • An inspection fails. Re-inspections are $35.00 and double for each subsequent re-inspection, so repeat failures escalate quickly.

The unresolved application-fee and plan-review question, pool electrical and other trade permits, pool barrier permitting, impact and utility fees, county charges, pool construction cost, zoning setbacks and HOA approvals are all excluded from the $242.00 on this page, and the page-standard disclaimer applies - always verify with the New Braunfels Building Division before budgeting.

New Braunfels Pool Permit Cost vs Other Verified Texas Cities

New Braunfels sits mid-range among verified Texas cities, but its figure is built differently: it already carries an inspection fee and a percentage technology fee that the flat-line cities do not. The table below is labelled peer context only.

City Pool Fee Basis In-Ground Pool Permit
New Braunfels, TX $200 flat + $35 inspection + 3% tech, rounded down $242.00
League City, TX Single flat pool line; trades separate $600.00
Beaumont, TX $225 in-ground + $50 pool plan review; MEP separate $275.00
Brownsville, TX Flat residential pool line; trades separate $200.00
Laredo, TX Flat building permit; trades separate $64.00

Scope note: New Braunfels' $242.00 already includes its $35.00 residential inspection fee and 3% technology fee, so it is closer to a true all-in figure than the flat-line cities. Beaumont's $275.00 includes its pool-specific $50.00 plan review but not its MEP trades. League City's $600.00, Brownsville's $200.00 and Laredo's $64.00 are single flat lines with trades and inspections billed separately. These are labelled peer figures for context, not a like-for-like all-in comparison. Confirm current figures and trade treatment with each department.

Next Step

See New Braunfels' full residential fee schedule, or compare another verified Texas city's pool permit.

Frequently Asked Questions

An in-ground pool is $242.00 all-in and an above-ground pool is $139.00 all-in. Those come from the printed Appendix D components: a $200.00 (or $100.00) flat pool fee, plus the $35.00 residential inspection fee, plus the 3% information-technology fee, with the result rounded down to the whole dollar. Pool electrical is separate at a $12.50 swimming pool circuit plus a $15.00 issuance fee.
Step by step from the ordinance: $200.00 in-ground pool fee + $35.00 residential inspection fee = $235.00. The 3% technology fee adds $7.05, giving $242.05. Appendix D Sec. B(k) rounds permit fees down to the whole dollar, so the result is $242.00. The above-ground path is $100.00 + $35.00 = $135.00, plus 3% = $139.05, rounded down to $139.00.
No. Schedule A Residential prints the pool lines as flat amounts - $200.00 in ground, $100.00 above ground - with no square-foot or valuation tier. New Braunfels does price new residential construction per square foot at $0.50/sq ft, and prices commercial work by valuation, but pools are flat.
The ordinance does not say. Both are printed in Appendix D Sec. A as applying to "all new construction, additions and substantial alterations", and whether a standalone residential pool falls in that bucket is a Building Division determination. Because the text is silent, this page publishes $242.00 without them. If the department applies both, the figure would be $345.00 - shown explicitly as a labelled conditional scenario in Example 4 rather than hidden.
The electrical schedule prints a swimming pool circuit at $12.50, plus a $15.00 issuance fee - so a single-circuit pool adds $27.50, bringing an in-ground project to $269.50. That is notably cheap in peer terms: Beaumont carries a $70.00 electrical minimum and League City a $59.00 base. Additional circuits are $10.00 each and residential panels run $20.00 to $65.00 by circuit count.
It is a City of New Braunfels information-technology fee printed in Appendix D, Sec. A, charged at 3% on all review, building, zoning and development related fees. It is a municipal charge, not a state levy - Texas has no statewide percentage permit levy. On a pool it adds $7.05 to the in-ground path and $4.05 to the above-ground path before the round-down.
Appendix D prints a general residential "Fence - $50.00" line but no pool-barrier or pool-enclosure line item, so no pool-barrier fee is published here. Texas requires a compliant residential pool barrier; how New Braunfels permits and prices it for a pool project is a determination for the Building Division. No figure is invented.
This is a real limitation. Appendix D carries no effective date of its own; the amendment history for the building-permitting section ends at Ord. No. 2023-76, Sec. 4, adopted October 9, 2023 - roughly 33 months before the July 2026 extraction and past our 24-month currency threshold. The Municode page is labelled current (version May 28, 2026), and a city newsflash confirms Council amended development-related fees effective April 1, 2024. One more disclosure: an older "2018 Fees" PDF is still linked from the city's Building Permits page, showing a superseded valuation-tiered residential table - it was not used for any figure here. Confirm current amounts with the Building Division. See all New Braunfels permit fees.

Who to Contact

Department City of New Braunfels - Building Division (Comal and Guadalupe Counties, TX)
What to ask Whether a standalone pool draws the $50.00 application fee and the 25% plan review, whether the codified amounts are still current after the April 1, 2024 fee amendments, how many electrical circuits your pool will be charged for, and how a pool safety barrier is permitted.
Fee schedule Code of Ordinances, Appendix D - Fee Schedule

Sources

Official Sources - Recorded July 2026
  • City of New Braunfels - Code of Ordinances, Appendix D - Fee Schedule New Braunfels, TX - official codified ordinance on the Municode code library, page-labelled "VERSION: MAY 28, 2026 (CURRENT)". Primary source for the $200.00 in-ground and $100.00 above-ground pool fees (Sec. B(a), Schedule A Residential), the $50.00 permit application fee, the 25%-of-permit-cost residential plan review, the $35.00 residential inspection fee, the 3% information-technology fee (Sec. A), and the round-down-to-whole-dollar rule (Sec. B(k)). Amendment history for the building-permitting section ends at Ord. No. 2023-76, Sec. 4, October 9, 2023 source age - last amended 2023, verify current
  • City of New Braunfels - official city website (Building Permits, Fee Amendments Customer Information Bulletin) New Braunfels, TX (.gov) - the city's own site, which confirms Council amended development-related fees effective April 1, 2024 and hosts the Building Division's permit pages. Also the location of a superseded "2018 Fees" PDF that was reviewed and deliberately NOT used for any figure on this page. Verified July 2026.
  • Texas Local Government Code, Chapter 214 Texas statute (.gov) confirming municipal building-regulation authority and that Texas imposes no statewide percentage building-permit levy. Context for the "no statewide levy" statement. Verified July 2026.
Always verify current pool permit fees directly with the City of New Braunfels Building Division before budgeting or filing. The figures on this page come from the codified Code of Ordinances, Appendix D, whose building-permitting amendment history ends at Ord. No. 2023-76, October 9, 2023, and a city bulletin confirms development-related fees were amended effective April 1, 2024. The $242.00 is the pool permit plus inspection and technology fees only. Ask specifically whether a standalone pool draws the $50.00 application fee and the 25% plan review, how many electrical circuits your pool will be charged for, and how a pool safety barrier is permitted.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by the City of New Braunfels Building Division at the time of application. The $200.00 in-ground pool fee, $100.00 above-ground pool fee, $35.00 residential inspection fee, 3% information-technology fee, round-down-to-whole-dollar rule, $50.00 application fee, 25% plan review, $12.50 swimming pool circuit and $15.00 electrical issuance fee are exact from the codified Appendix D; the $242.00, $139.00, $269.50 and $345.00 figures are arithmetic on those printed inputs. The $345.00 is a labelled conditional scenario that applies only if the department charges the application fee and plan review on a standalone pool - the ordinance does not state that it does, which is why $242.00 is the published answer. The building-permitting section was last amended October 9, 2023, roughly 33 months before extraction, and a city bulletin confirms an April 1, 2024 fee amendment, so amounts should be re-confirmed. A superseded "2018 Fees" PDF still linked from the city site was reviewed and not used. Trade permits beyond the single pool circuit, pool barrier permitting, water/wastewater/roadway impact fees, New Braunfels Utilities charges, Comal and Guadalupe County fees, pool construction cost, zoning setbacks and HOA approvals are all excluded. Verify all fees directly with the department before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.