Charlottesville, VA Building Permit Fees (2026)

Actual residential building permit fees from the City of Charlottesville Building Inspection Fee Schedule, cross-checked against the City's own online permit fee calculator. Read directly from the City's official sources on November 5, 2026.

Jurisdiction
City of Charlottesville, VA
Permit Type Covered
Building permit (residential) + trade permits
Coverage Scope
Value-based fee; maintenance fee; 2% state levy
Fee Schedule Effective
No effective date printed (fee lines dated "Mar-23")
Last Verified
November 5, 2026
Fee Status
Official City fee schedule
What This Page Covers - and What It Does Not

This page covers: The residential building and trade permit fees on the City of Charlottesville Building Inspection Fee Schedule. Building, electrical, mechanical, plumbing, gas and demolition permits all use one formula: $75 for a project valued up to $1,500, and above $1,500, $75 plus the 0.7% base rate times the project value. Every permit also carries a Permit System Maintenance Fee of $10 to $50, set by the size of the permit fee, and the 2.00% state levy that the schedule itself imposes. Charlottesville is an independent city: its Neighborhood Development Services Building Inspections Division issues these permits, separately from Albemarle County.

One point the schedule leaves open: the schedule applies the 2% levy to "the total fee," while the City's own online calculator applies it to the permit fee only, not to the maintenance fee. PermitPrice follows the City calculator, so the totals here could be $0.20 to $1.00 higher if the levy is also charged on the maintenance fee.

This page does NOT cover: zoning, site plan and subdivision fees, historic and corridor review fees, erosion and stormwater fees (other than the $150 single-family agreements noted below), water and sewer connection and tap fees, and commercial fees. These are excluded from every figure here.

Key Takeaways
  • Every building, electrical, mechanical, plumbing, gas and demolition permit is $75 up to $1,500 of value, then $75 plus 0.7% of the value.
  • A new home with a $300,000 building value: $2,175.00 permit fee + $50 maintenance fee + $43.50 levy = $2,268.50.
  • The fee is based on project value, not square footage, so the cost you declare drives the fee: each $10,000 of value adds $70.
  • The Permit System Maintenance Fee is $10, $20, $35 or $50, depending on whether the permit fee is under $200, under $500, up to $1,000 or over $1,000.
  • The schedule itself imposes a 2.00% state levy, required under the Virginia Uniform Statewide Building Code.
  • Working without a permit doubles the permit fee; a "not ready" inspection is $100, and reinspections are $100 starting after the 2nd inspection of the same violation.

Charlottesville is not in the PermitPrice calculator yet, because its maintenance fee is a flat amount chosen by the size of the permit fee. Use the formula and worked examples on this page, or the City's own online permit fee calculator linked in the sources.

Charlottesville Building Permit Fee Structure

Charlottesville sets its building fees in the Building Inspection Fee Schedule (Building Regs, Chapter 5). The schedule names one Building Inspections Base Rate (BR), the "rate that permit fees are based on," and the City's online calculator sets it at 0.007 (0.7%). The tables below show the residential figures before the maintenance fee and state levy.

Permit fees by project value

Permit Fee
Building permit - project value up to $1,500$75
Building permit - project value over $1,500$75 + 0.7% of project value
Electrical, mechanical, plumbing and gas permits (each on its own value)$75 min; over $1,500: $75 + 0.7% of full value
Demolition permit$75 min; over $1,500: $75 + 0.7% of full value
Electric / plug-in vehicle charger$75 min; over $1,500: $75 + 0.7% of full value
Tank removal or installation (UST or AGST)$75 min; over $1,500: $75 + 0.7% of full value
Residential electrical repairs under $1,000 (repair or replace existing outlets and switches only)$75
Amendment to an issued permit$75 min; over $1,500: $75 + 0.7% of full added value
Manufactured trailer change-out (single or double wide)$150
Working without a permitPermit fee x 2

The schedule's wording is "$75 Fee Based on project value up to $1,500. Over $1,500 of project value, Fee is $75 plus project value multiplied by BR." The City's online calculator applies the 0.7% to the full project value, not just the part above $1,500, so a $1,501 job is $75 + $10.51 = $85.51. The base-rate cell on the posted schedule is a scanned image that reads ".7" followed by an unclear character; PermitPrice uses the 0.007 rate written into the City's own calculator.

Permit System Maintenance Fee (applies to all permits)

Permit fee Maintenance fee Project value that produces it
Under $200$10Up to about $17,857
$200 - $499.99$20About $17,858 to $60,714
$500 - $1,000$35About $60,715 to $132,142
Over $1,000$50Over about $132,143

The value column is PermitPrice arithmetic from the $75 + 0.7% formula, rounded to the dollar. When several permits are priced together, the City's online calculator applies one maintenance fee to their combined permit fees; the schedule says only that the fee "applies to all permits." The examples on this page price one permit at a time.

Inspection, occupancy and other fees

Fee Amount
Reinspection (starts after the 2nd inspection of the same violation)$100
Not-ready fee (inspection cannot be done because work is not finished)$100
Stop work order$150 per day until work stops
Code modification application - residential / commercial and others$75 / $150
Certificate of occupancy not required by the USBC - single family / other$60 / $125
Non-refundable portion of a permit fee - value up to $2,000 / over $2,000$25 / $75
Building Code Board of Appeals application$250

Charlottesville Permit Fee Components

A Charlottesville residential permit is the value-based fee (or the $75 minimum), plus the Permit System Maintenance Fee, plus the 2% state levy. There is no separate plan review fee on the residential schedule.

Component Amount Status
Permit fee $75 up to $1,500; above that, $75 + 0.7% of full value Exact from the Building Inspection Fee Schedule and City calculator
Permit System Maintenance Fee $10 / $20 / $35 / $50 Exact; tier set by the permit fee
Virginia state levy 2.00% Rate exact from the schedule; base follows the City calculator (permit fee only)
Trade permits (electrical, mechanical, plumbing, gas) Same formula, each on its own value Separate permits when a permit is required; each carries the levy. PermitPrice adds one maintenance fee per permit; the City calculator applies one to the combined fees
Zoning, historic, stormwater, utility fees Separate schedules Excluded from every figure on this page

How the totals on this page are built: permit fee + maintenance fee + (permit fee x 2%). For a $300,000 new home that is $2,175.00 + $50.00 + $43.50 = $2,268.50. The schedule says the 2.00% surcharge is imposed "as required under state law," which is the levy set by USBC 13VAC5-63-70 (Section 107.2) under Code of Virginia 36-137(7). The schedule applies it to "the total fee"; the City's online calculator charges it on the permit fee only, and PermitPrice follows the calculator.

Worked Examples

Every rate below is exact from the City of Charlottesville Building Inspection Fee Schedule and the City's online calculator. The project values are illustrative inputs; your fee follows the value the City accepts for your job.

Example 1: New Single-Family Home, $300,000 Building Value

Fee Calculation - New Home, Building Permit (Charlottesville Building Inspections)
Fee Component Rule Applied Amount
Building permit fee $75 + $300,000 x 0.7% $2,175.00
Permit System Maintenance Fee permit fee over $1,000 $50.00
Virginia state levy $2,175.00 x 2% $43.50
Building permit total fee + $50 + 2% $2,268.50

Assumptions: The $300,000 building value is an illustrative input; the schedule bases the building permit on project value, with trade values priced on their own permits. Electrical, mechanical, plumbing and gas work, where a permit is required, each need a separate permit at the same formula on that trade's value. If you price them one by one, each adds its own maintenance fee; the City calculator instead applies one maintenance fee to the combined permit fees, which can be lower (a $2,175.00 building fee plus four $75 trade permits is $50 combined versus $90 counted per permit). Zoning, stormwater and utility connection fees are not included. Source: City of Charlottesville Building Inspection Fee Schedule.

Example 2: Home Addition Valued at $80,000

Fee Calculation - Residential Addition
Fee Component Rule Applied Amount
Building permit fee $75 + $80,000 x 0.7% $635.00
Permit System Maintenance Fee permit fee $500 - $1,000 $35.00
Virginia state levy $635.00 x 2% $12.70
Building permit total fee + $35 + 2% $682.70

Assumptions: The $80,000 value is an illustrative input. Charlottesville does not price additions by square footage, so a larger or more expensive addition pays more even at the same size. Trade permits for the addition are separate. Source: City of Charlottesville Building Inspection Fee Schedule.

Example 3: Deck Valued at $15,000

Fee Calculation - Residential Deck in Charlottesville
Fee Component Rule Applied Amount
Building permit fee $75 + $15,000 x 0.7% $180.00
Permit System Maintenance Fee permit fee under $200 $10.00
Virginia state levy $180.00 x 2% $3.60
Deck permit total fee + $10 + 2% $193.60

Assumptions: The $15,000 deck value is an illustrative input. Any deck valued at about $17,857 or less keeps the permit fee under $200 and pays the $10 maintenance fee. Source: City of Charlottesville Building Inspection Fee Schedule.

Example 4: Remodel, Demolition and Small Jobs

Fee Calculation - Small Residential Permits in Charlottesville
Project Rule Applied Fee
Kitchen remodel valued at $40,000 (building permit) $355.00 ($75 + $280.00) + $20 + $7.10 $382.10
Demolition valued at $8,000 $131.00 ($75 + $56.00) + $10 + $2.62 $143.62
Any permit valued at $1,500 or less $75 + $10 + $1.50 $86.50
Residential electrical repair under $1,000 $75 flat + $10 + $1.50 $86.50

Assumptions: The remodel and demolition values are illustrative inputs. The remodel figure covers the building permit only; electrical, plumbing or mechanical work in the kitchen, where a permit is required, needs its own permit at the same formula. The $75 electrical repair line covers repairing or replacing existing outlets and switches only, not new work. Source: City of Charlottesville Building Inspection Fee Schedule.

Read before you budget from these examples

  • The levy base follows the City calculator: the schedule applies 2.00% to "the total fee," but the City's calculator charges it on the permit fee only. If the levy is also charged on the maintenance fee, add $0.20 to $1.00.
  • Several permits priced together: the City's calculator applies one maintenance fee to the combined permit fees of every permit entered together, which can differ from adding one maintenance fee per permit.
  • A permit fee of exactly $500.00: the schedule puts it in the $35 maintenance tier; the City calculator charges $20. No example here falls on that boundary.
  • Trade permits are extra: where electrical, mechanical, plumbing or gas work needs a permit, it is a separate permit priced on its own value, with the levy. Whether each adds its own maintenance fee or one fee covers the combined total is not settled (see above).

Practitioner Insight

Charlottesville's formula has a step at $1,500. Up to $1,500 the fee is a flat $75, but once a job is valued above $1,500 the 0.7% applies to the whole value and is added on top of the $75, so a $1,501 job is $85.51. Past that point the fee rises smoothly: $70 for every $10,000 of value. Because the fee follows value rather than size, two additions of the same square footage can pay very different fees, and the value you declare on the application is what the City prices.

The surrounding county works differently. Albemarle County permit fees price new homes by size tier and additions and decks by the square foot, so check which locality your address is in before you budget. For other Virginia cities that charge by value, compare Richmond permit fees and Lynchburg permit fees.

Permit Requirements - Common Residential Projects in Charlottesville

Project Type Permit Required? Fee Category Notes
New single-family home Yes $75 + 0.7% of value $300,000 value: $2,268.50 building permit; trade permits separate
Addition Yes $75 + 0.7% of value $80,000 value: $682.70
Deck Yes $75 + 0.7% of value $15,000 value: $193.60
Electrical, mechanical, plumbing or gas work Separate trade permit when required $75 min; over $1,500: $75 + 0.7% of full value Each trade priced on its own value
Electric vehicle charger Yes $75 min; over $1,500: $75 + 0.7% of full value Listed separately on the schedule
Demolition Yes $75 min; over $1,500: $75 + 0.7% of full value $8,000 value: $143.62
Shed, fence, re-roof, window replacement Ask Building Inspections Same formula if a permit is required Whether a permit is needed is set by the Virginia USBC

Which projects need a permit, and which fee line applies, is decided by the Charlottesville Building Inspections Division under the Virginia Uniform Statewide Building Code. New permits submitted since January 18, 2025 are reviewed under the 2021 USBC cycle. Properties in an architectural design control or historic conservation district may also need historic review, which has its own fee. When unsure, contact Building Inspections before starting work.

Charlottesville Building Inspections

Office

Building Inspections Division, Neighborhood Development Services

City Hall, first floor, 605 E Main Street, Charlottesville, VA 22902 · 434-970-3008

Email

Permits@charlottesville.gov

Inspections: Inspections@charlottesville.gov

Apply

City Public Permit Portal

Building and trade permits, fee payment and inspection requests are handled through the City Public Permit Portal

Verify with your local building department before budgeting or filing. The fees on this page are from the City of Charlottesville Building Inspection Fee Schedule and the City's online permit fee calculator, read on November 5, 2026. Fees can change. Confirm the amounts, the project value the City will use, how the maintenance fee and state levy are applied to your permits, and whether historic or zoning review applies with Building Inspections (434-970-3008) before treating any total here as final.

When This Estimate May Not Apply

The City values your project differently

Every fee here follows project value. If the City uses a higher value than you expect, the fee rises by $70 for every $10,000, and the maintenance fee may move up a tier.

The levy is charged on the maintenance fee too

The schedule applies 2.00% to "the total fee"; the City calculator charges it on the permit fee only. If the levy also covers the maintenance fee, each total here rises by $0.20 to $1.00.

You file several permits together

The City calculator applies one maintenance fee to the combined permit fees of all permits priced together. That can differ noticeably from adding one maintenance fee per permit: a $2,175.00 building fee plus four $75 trade permits is $50 combined, or $90 counted per permit. Ask Building Inspections which method applies to your permits.

The schedule is updated

The posted schedule prints no effective date; each building-fee line carries the approval date "Mar-23." The City can change these fees, so a newer schedule would change every figure here.

Work starts early or inspections fail

Working without a permit doubles the permit fee. A stop work order is $150 per day, a "not ready" inspection is $100, and reinspections are $100 starting after the 2nd inspection of the same violation.

Site, historic and utility fees apply

A single-family erosion and sediment control agreement in lieu of a plan is $150, and a stormwater management agreement in lieu of a plan is $150, where those apply. Historic review in a design control district ($100 to $375) and water and sewer tap fees are separate. None of these are in the totals on this page.

Source note: Fees come from the City of Charlottesville Building Inspection Fee Schedule (Building Regs, Chapter 5), the PDF linked as "Building Permit Fee Schedule" from the Building Inspections page. Its building-fee pages are a scanned image, so the 0.7% base rate was confirmed against the City's official online permit fee calculator, which uses 0.007, the same $75 minimum, the same maintenance tiers and a 2% levy. Read on November 5, 2026.

Frequently Asked Questions

The building permit is $75 plus 0.7% of the building value. For a $300,000 building value that is $2,175.00, plus the $50 Permit System Maintenance Fee and the 2% state levy ($43.50), for a total of $2,268.50. Where electrical, mechanical, plumbing or gas work needs a permit, it is a separate permit at the same formula on that trade's value.
The minimum is $75, which covers any project valued up to $1,500. With the $10 maintenance fee and the 2% levy ($1.50), a minimum permit is $86.50.
Decks are priced by value, like every other building permit. A $15,000 deck is $75 + $105.00 = $180.00, plus the $10 maintenance fee and the $3.60 levy, for $193.60. Any deck valued at about $17,857 or less pays the $10 maintenance tier.
It is a flat fee the schedule applies to all permits, set by the size of the permit fee: $10 for permits under $200, $20 from $200 to $499.99, $35 from $500 to $1,000, and $50 over $1,000. The City's online calculator applies one maintenance fee to the combined permit fees when several permits are priced together.
Yes. The schedule imposes a surcharge of 2.00% "as required under state law," the levy set by USBC 13VAC5-63-70 (Section 107.2) under Code of Virginia 36-137(7). The schedule applies it to "the total fee"; the City's online calculator charges it on the permit fee only, which is how PermitPrice computes it.
The Building Inspection Fee Schedule has no separate residential plan review line. If a permit is cancelled while reviews are underway and no inspection has been scheduled or completed, the schedule keeps a non-refundable $25 (project value up to $2,000) or $75 (over $2,000).
PermitPrice read the schedule linked from the City's Building Inspections page and the City's online permit fee calculator on November 5, 2026. The schedule prints no effective date; each building-fee line carries the approval date "Mar-23." See other localities on the Virginia permit fees hub, including Albemarle County permit fees and Lynchburg permit fees.

Sources

Official Sources · Verified November 2026
Next Step

Price your Charlottesville project with the formula above, or compare fees with nearby Central Virginia localities.

Virginia Permit Cost Guide → Virginia Deck Permit Guide → All Permit Guides → Henrico County Fees → Hanover County Fees → How We Calculate Fees → Our Official Sources → All Virginia Jurisdictions →

Permit Fees Are One Part of Your Project Budget

Once you know your Charlottesville permit cost, two related numbers round out your total budget picture:

Property tax impact after your project closes

A permitted addition or new home may change the property's assessed value in Charlottesville. The City's real estate assessment office determines that value, separately from this permit fee.

Zoning, historic, utility and stormwater fees for larger projects

Charlottesville's Neighborhood Development Services and Public Works fee schedule sets zoning, site plan, historic review and stormwater charges separately, and utility tap fees come from the City's utilities. They are excluded from the figures above.

These charges are administered separately from the building permit fee, though the responsible office and billing process vary by jurisdiction. See which tool covers each charge →

Always verify current fees directly with Charlottesville Building Inspections before budgeting or filing. The fees on this page are from the City of Charlottesville Building Inspection Fee Schedule and the City's online permit fee calculator. Fees can change. Confirm the project value the City will use, how the maintenance fee and state levy are applied, and the current amounts with Building Inspections (434-970-3008) before you file.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by the City of Charlottesville at the time of application. The $75 minimum, the 0.7% base rate, the Permit System Maintenance Fee tiers, the 2.00% state levy rate and the inspection and other fees are exact from the City's Building Inspection Fee Schedule and online calculator. The levy base (permit fee only) follows the City calculator, while the schedule says "total fee." Project values in the examples are illustrative inputs. Zoning, historic, stormwater and utility fees are not included in any total on this page. Verify all fees directly with Building Inspections before filing.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.