Shed Permit Cost in Carrollton, TX (2026)

Storage shed permit fees for the City of Carrollton, Texas (Denton, Dallas, and Collin counties), pulled directly from the Code of Ordinances, Chapter 31 – Comprehensive Fee Schedule, Sec. 31.01(B) Building Inspection. The schedule prints a single stand-alone "Storage shed" line at a flat $50.00 – the same $50.00 charged for a fence or a retaining wall. That $50.00 is a "specific permit," so it is not the $125.00 nonrefundable application fee that Carrollton attaches to project permits such as new dwellings and additions. The $50.00 does not include electrical or plumbing; if you run power to the shed, a separate electrical permit applies at $4.00 per $1,000 of valuation with a $75.00 minimum. Texas has no statewide permit levy and Carrollton adds no technology surcharge. One caution controls this page: the fee schedule is a live codification current through December 2, 2025 with no printed effective date on the fee lines, so confirm the current amount with Building Inspection before budgeting.

Storage Shed Permit
$50.00 flat (exact printed line)
Application Fee (project permits)
$125.00 – not added to a stand-alone shed
Electrical (if wiring the shed)
Separate permit, $75.00 minimum
Technology / State Levy
None (Texas has no state levy)
Fee Basis
Code Ch. 31, Sec. 31.01(B) specific permit
Fee Schedule Effective
Codified, no printed date – verify current
What This Guide Covers - and What It Does Not

This guide covers: The City of Carrollton, Texas (Denton, Dallas, and Collin counties) stand-alone "Storage shed" permit line as printed in the Code of Ordinances, Chapter 31, Sec. 31.01(B) Building Inspection – a flat $50.00 specific permit. That $50.00 is exact from the published codified schedule. It is the building permit for the shed structure itself.

The $125.00 application fee is not added to a stand-alone shed: Carrollton's $125.00 nonrefundable application fee is printed for project permits – new dwellings, additions, remodels, and finish-outs. A stand-alone backyard storage shed is a "specific permit," which the schedule lists separately at $50.00, so the $125.00 application fee is not part of this line. If the shed is filed as part of a larger project the department classifies as a project permit, that could change – a conditional case to confirm.

Electrical and plumbing are not included: the $50.00 storage-shed line is the building permit only. If you run power to the shed – lighting, an outlet, or a subpanel – a separate electrical permit applies at $4.00 per $1,000 of valuation with a $75.00 minimum. That would make a wired shed roughly $125.00 across the two permits – a labeled estimate, not a single printed line.

A large or permanent accessory building may be classed differently: the same schedule prices "accessory buildings" under a project line at $6.00 per $1,000 of valuation (minimum $125.00). A modest prefab or site-built backyard storage shed matches the flat $50.00 "Storage shed" specific-permit line; a large, permanent, or habitable accessory structure (a workshop or detached garage-style building) may instead fall under the valuation line. This is an ambiguity in the schedule – confirm which line governs your structure with Building Inspection.

Source-age caution: the Chapter 31 fee schedule is a live eCode360 codification current through December 2, 2025, but the individual fee subsections do not print their own adoption or effective date. Treat the $50.00 as current-as-codified and confirm the adopting ordinance amount with Building Inspection before budgeting.

This guide does NOT cover: zoning setback, easement, and rear-yard placement rules; homeowners-association approval; concrete slab or foundation work if the shed sits on a permanent foundation; impact fees; the separate electrical, plumbing, mechanical, or irrigation permits; and any Denton, Dallas, or Collin county fees.

Key Takeaways
  • Carrollton, Texas prints a stand-alone "Storage shed" permit at a flat $50.00 in the Code of Ordinances, Chapter 31, Sec. 31.01(B) Building Inspection. That $50.00 is the exact printed figure and it matches the $50.00 fence and retaining-wall specific permits.
  • The $125.00 nonrefundable application fee is printed for project permits – new dwellings, additions, remodels, and finish-outs – not a stand-alone shed. It is not added to the $50.00 storage-shed line unless the shed is filed as part of one of those larger projects.
  • The $50.00 does not include electrical. If you power the shed, a separate electrical permit applies at $4.00 per $1,000 of valuation with a $75.00 minimum, making a wired shed roughly $125.00 across the two permits – a labeled estimate, not a printed total.
  • A large or permanent accessory building may instead be priced under the "accessory buildings" project line at $6.00 per $1,000 of valuation (minimum $125.00). Confirm which line governs your structure with Building Inspection.
  • Texas has no statewide percentage permit levy and Carrollton adds no technology surcharge, so the $50.00 stands on its own for a stand-alone shed with no wiring.
  • The Chapter 31 fee schedule is codified current through December 2, 2025 with no printed effective date on the fee lines – confirm current amounts with Building Inspection. For same-city context, see the Carrollton fence permit guide and the Carrollton solar permit guide.

Carrollton Shed Permit Fee Structure

The storage shed permit is a single flat line at $50.00 – the exact printed "Storage shed" specific permit. There is no per-square-foot scaling on that line and no statewide levy or technology surcharge. The table below shows the shed line, the items that are commonly confused with it (the $125.00 application fee and the electrical permit), and the larger-accessory-building valuation line, so you can see what is and is not part of the $50.00. Every printed amount is exactly as it appears on the schedule.

Item Fee How It Is Applied
Storage shed (specific permit) $50.00 flat Exact printed line in Chapter 31, Sec. 31.01(B). The building permit for a stand-alone backyard storage shed, any size, as listed.
Application fee (project permits) $125.00 - not added Nonrefundable, printed for new dwellings, additions, remodels, and finish-outs. A stand-alone shed is a specific permit, so it is excluded here.
Electrical permit (if wiring) $4.00 / $1,000 (min $75.00) Separate permit if you run power to the shed. Not bundled into the $50.00. Adds about $75.00 for a small job.
Large / permanent accessory building $6.00 / $1,000 (min $125.00) The "accessory buildings" project line. May govern a large, permanent, or habitable structure instead of the flat $50.00 shed line. Confirm with the city.
Fence / retaining wall (context) $50.00 each Sibling specific permits at the same $50.00 as the storage shed. Shown for context, not added.
State / city percentage levy None Texas has no statewide permit levy and Carrollton adds no technology surcharge to the shed line.

Source: City of Carrollton (TX) Code of Ordinances, Title III, Chapter 31 – Comprehensive Fee Schedule, Sec. 31.01(B) Building Inspection, read from the eCode360 codification current through December 2, 2025. The $50.00 storage-shed line, the $125.00 application fee, the $4.00 per $1,000 electrical permit (min $75.00), and the $6.00 per $1,000 accessory-building line (min $125.00) all appear on the city schedule. The fee subsections do not print their own effective date – confirm the current amount and which line governs your structure with Building Inspection.

Worked Examples - Real Shed Projects in Carrollton

The storage-shed permit is a flat $50.00, so the building line does not change with the size of a typical backyard shed. What changes the out-the-door cost is whether you add power and whether the structure is large enough to be classed as an accessory building. Each example below separates the exact printed line from any labeled estimate.

Example 1: Standard prefab backyard shed, no power

A homeowner sets a 10 ft x 12 ft (120 sq ft) prefab storage shed on a gravel pad, no electrical.

  • Storage shed specific permit: $50.00
  • Application fee ($125.00): not added (project permits only)
  • Electrical: not added (no wiring)
  • Total: $50.00

The $50.00 is the exact printed "Storage shed" line. Setback and placement rules still apply, but they carry no fee on this line.

Example 2: Shed with lighting and an outlet

The same shed, but the owner runs a circuit from the house for lighting and one outlet.

  • Storage shed specific permit: $50.00
  • Electrical permit ($4.00 / $1,000, min $75.00): $75.00
  • Estimate: $125.00

The $50.00 shed line is exact; the $75.00 electrical minimum is the printed floor for a small job. The $125.00 combined figure is a labeled estimate across two separate permits, not one printed total.

Example 3: Large permanent workshop (valuation line)

A homeowner builds a 500 sq ft site-built, foundation-set workshop the department classes as an accessory building at, say, $30,000 valuation.

  • Accessory building ($6.00 / $1,000 of valuation): $30,000 ÷ 1,000 × $6.00 = $180.00
  • Minimum check: $180.00 is above the $125.00 minimum, so $180.00 applies
  • Electrical, if wired: separate $75.00 minimum
  • Estimate: $180.00 building (plus trades)

This is the conditional case where the flat $50.00 shed line does not apply. Whether a structure is a $50.00 "Storage shed" or a valuation-priced accessory building is a department call – confirm before budgeting.

When This Estimate May Not Apply

The $50.00 covers the stand-alone "Storage shed" specific permit as printed. Route your project to Building Inspection before relying on this figure if any of the following applies:

  • Your structure is large, permanent, or habitable. A workshop, detached garage, or foundation-set accessory building may be priced under the $6.00 per $1,000 valuation line (minimum $125.00) rather than the flat $50.00 shed line. Confirm which line governs.
  • You are wiring or plumbing the shed. The $50.00 is the building permit only. Electrical is a separate permit at $4.00 per $1,000 of valuation ($75.00 minimum); plumbing, if any, is a separate $75.00-minimum permit too.
  • The shed is part of a larger project. If it is filed with new construction, an addition, or a remodel, the $125.00 nonrefundable application fee attached to project permits may apply. A stand-alone shed is normally a specific permit and does not carry it.
  • The codified amount has been amended. The Chapter 31 schedule is current through December 2, 2025 but prints no effective date on the fee lines. Confirm the current amount before budgeting.
  • Zoning, placement, or HOA rules affect your shed. Setback, easement, rear-yard coverage, and homeowners-association rules can restrict where or how large a shed may be. Those are separate from the $50.00 building fee.
  • You are in a Neighborhood Empowerment Zone or on exempt property. The schedule waives building permit fees for certain public and program properties. Confirm eligibility with the city.

Zoning and placement rules, HOA approval, slab or foundation work, impact fees, separate trade permits, and any Denton, Dallas, or Collin county fees are excluded from the $50.00 shed figure on this page, and the page-standard disclaimer applies. Because the schedule prints no effective date, always verify the current amount with Carrollton Building Inspection before budgeting.

Carrollton Shed Permit Cost vs Other Verified Texas Cities

Texas cities price shed and accessory-building permits differently – some as a single flat fee, some tiered by size, some by valuation. Scope differs, so each figure below notes its basis, and each department should be verified separately.

City Shed / Accessory Fee Basis Typical Backyard Shed Permit
Carrollton, TX Flat "Storage shed" specific permit $50.00 flat
Arlington, TX Flat if ≤320 sq ft; valuation above $25.00 (≤320 sq ft)
Grand Prairie, TX Tiered by size $20 / $100 / $0.25 per sq ft
New Braunfels, TX Flat, site-built vs pre-built $75 / $50 (~$113 all-in)

Scope note: Carrollton charges a flat $50.00 stand-alone "Storage shed" specific permit. Arlington charges $25.00 for a portable storage or accessory building 320 square feet or under, moving to a valuation basis above that. Grand Prairie tiers its accessory-building fee by size ($20.00 up to 100 sq ft, $100.00 for 100–400 sq ft, $0.25 per sq ft above). New Braunfels charges $75.00 site-built or $50.00 pre-built, plus fees. Compare the basis, not just the number, and confirm current figures with each department.

Next Step

See Carrollton's full fee schedule, or price other Carrollton projects.

Frequently Asked Questions

A stand-alone storage shed is a flat $50.00 "Storage shed" specific permit in the Carrollton Code of Ordinances, Chapter 31, Sec. 31.01(B) – the exact printed line, the same $50.00 as a fence or retaining wall. That covers the building permit for the shed structure. If you wire the shed, a separate electrical permit adds a $75.00 minimum, making a powered shed about $125.00 across two permits. The schedule is codified with no printed effective date, so confirm the current amount with Building Inspection.
Not for a stand-alone shed. Carrollton's $125.00 nonrefundable application fee is printed for project permits – new dwellings, additions, remodels, and finish-outs. A backyard storage shed is a "specific permit," listed separately at $50.00, so the $125.00 is not part of that line. It could apply only if the shed is filed as part of a larger project the department classifies as a project permit. Confirm with Building Inspection.
No. The $50.00 storage-shed line is the building permit only. If you run power to the shed – lighting, an outlet, or a subpanel – a separate electrical permit applies at $4.00 per $1,000 of valuation with a $75.00 minimum. A wired shed is therefore roughly $125.00 across the two permits. That combined figure is a labeled estimate, not a single printed line.
The flat "Storage shed" line is $50.00 as printed, without a size tier, so a typical backyard shed is $50.00 regardless of a few extra square feet. The size question matters only when a structure is large, permanent, or habitable enough that the department treats it as an accessory building – then the $6.00 per $1,000 of valuation line (minimum $125.00) can govern instead. Confirm which line applies with Building Inspection.
The schedule prints a flat $50.00 "Storage shed" specific permit and, separately, prices "accessory buildings" under a project line at $6.00 per $1,000 of valuation (minimum $125.00). A modest prefab or site-built backyard shed matches the flat $50.00 line; a large, permanent, or habitable structure such as a workshop may fall under the valuation line. The schedule does not draw a bright-line size, so this is a department determination – ask before assuming $50.00.
No. Texas has no statewide percentage building-permit levy, and the Carrollton schedule adds no technology or automation surcharge to the storage-shed line. For a stand-alone shed with no wiring, the $50.00 stands on its own. Only a separate electrical permit (or the valuation line for a large accessory building) would add to it.
Yes. The $50.00 covers only the building permit fee. Zoning setback, easement, and rear-yard coverage rules govern where and how large a shed may be, and a homeowners association may add its own approval. Those requirements are separate from the fee and carry no charge on this line, but they can still stop or resize a project – check them before you buy the shed.
They come from the Code of Ordinances, Chapter 31, Sec. 31.01(B) Building Inspection, read from the eCode360 codification current through December 2, 2025. The individual fee subsections do not print their own adoption or effective date, so treat the $50.00 as current-as-codified and confirm the amount with Building Inspection before filing. See all Carrollton permit fees and all Texas cities.

Who to Contact

Department City of Carrollton, Texas - Building Inspection
County Denton, Dallas, and Collin counties, Texas
Official site City of Carrollton - Building Inspection
Ask them Whether your structure is a flat $50.00 "Storage shed" or a valuation-priced accessory building, whether a separate electrical permit is needed, whether the $125.00 application fee applies, and whether the codified amount has changed
Fee schedule Carrollton Code of Ordinances, Chapter 31 - Comprehensive Fee Schedule (eCode360)

Sources

Official Sources - Recorded August 2026
  • City of Carrollton, TX - Code of Ordinances, Chapter 31 (Comprehensive Fee Schedule) Carrollton, TX (Denton, Dallas, and Collin counties) - official codified Comprehensive Fee Schedule, Sec. 31.01(B) Building Inspection, on eCode360. Primary source for the $50.00 storage-shed line, the $125.00 application fee, the $4.00 per $1,000 electrical permit (min $75.00), and the $6.00 per $1,000 accessory-building line (min $125.00). Codification current through December 2, 2025; fee subsections print no individual effective date; recorded August 2026 Codified, no printed date - verify current
  • Texas Local Government Code, Chapter 214 Texas statute (.gov) confirming municipal building-regulation authority and that Texas imposes no statewide percentage building-permit levy. Context for the "no statewide levy" statement. Verified August 2026.
Always verify current storage shed permit fees directly with the City of Carrollton (TX) Building Inspection before budgeting or filing. The figures on this page come from the Code of Ordinances, Chapter 31, Sec. 31.01(B) Building Inspection, read from the eCode360 codification current through December 2, 2025. The schedule prints a flat $50.00 "Storage shed" specific permit; the $125.00 application fee is printed for project permits, not a stand-alone shed; and electrical wiring is a separate permit at a $75.00 minimum. The fee subsections carry no printed effective date, so confirm the current amount and whether your structure is a $50.00 shed or a valuation-priced accessory building before submitting.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by the City of Carrollton, Texas Building Inspection at the time of application. The $50.00 storage-shed specific permit, the $125.00 nonrefundable application fee, the $4.00 per $1,000 electrical permit (minimum $75.00), and the $6.00 per $1,000 accessory-building line (minimum $125.00) are as printed in the Code of Ordinances, Chapter 31, Sec. 31.01(B); that codification is current through December 2, 2025 and the fee subsections carry no individual effective date, so confirm current amounts. The $50.00 is the exact printed line for a stand-alone shed; the ~$125.00 wired-shed figure and the $180.00 accessory-building example are labeled estimates that add a separate electrical permit or apply the valuation line. The $125.00 application fee is printed for project permits and is excluded from a stand-alone shed. Zoning setback and placement rules, HOA approval, slab or foundation work, impact fees, separate trade permits, and any Denton, Dallas, or Collin county fees are separate and excluded. Verify all fees directly with the department before filing.