How Much Is a Remodel Permit? (2026)
What a building permit costs for an interior remodel ($30,000 construction value, 300 sq ft of work area), compared across every jurisdiction PermitPrice has verified, with the formula behind each number and how to find the current rate where you live.
A remodel permit costs between $75.00 and $1,008.00 for an interior remodel ($30,000 construction value, 300 sq ft of work area) across the 25 jurisdictions PermitPrice has verified in MD, TX, VA. The median is $220.00. There is no national or statewide fee: every county and city sets its own, and the 13x spread in this table comes from different pricing methods, not from the project.
- Across 25 verified jurisdictions, a permit for an interior remodel ($30,000 construction value, 300 sq ft of work area) runs from $75.00 (Grand Prairie, TX) to $1,008.00 (Fairfax County, VA). The median is $220.00.
- 3 of the 25 charge a flat fee, from $152.00 to $402.90. 8 price it on the project value; 14 price it by floor area or size tier.
- A remodel needs a building permit when it changes structure, walls, egress, or layout. Cosmetic work (paint, flooring, cabinets in the same place) is exempt in most places; the exemption list is set locally and stated on each jurisdiction page.
- Kitchen and bathroom remodels usually add separate electrical, plumbing and mechanical permits, each with its own fee. Those trade permits are not in any total on this page. The building permit fee alone is what this page compares.
- Every figure here is computed by PermitPrice's calculator engine from the jurisdiction's own published fee schedule with the same inputs; the effective date of each schedule is shown in the table. 4 of the 25 rows are computed from schedules dated before 2024 and 3 from schedules with no printed date; those are flagged.
This guide covers: the residential building permit fee for an interior remodel ($30,000 construction value, 300 sq ft of work area), computed with the same inputs for every jurisdiction in PermitPrice's verified calculator data that publishes a fee line for this project type (25 jurisdictions). Size-based schedules use the square footage, value-based schedules use the dollar value, and flat-fee schedules ignore both. Each row links to the jurisdiction page with the full schedule and the official source.
This guide does NOT cover: trade permits (electrical, plumbing, mechanical), zoning or setback review, HOA approval, impact or utility connection fees, reinspection fees, or commercial work. Kitchen and bathroom remodels usually add separate electrical, plumbing and mechanical permits, each with its own fee. Those trade permits are not in any total on this page.
Coverage note: PermitPrice covers Virginia, Maryland, Texas and Washington, DC. Jurisdictions outside those states, and covered jurisdictions whose schedule has no separate line for this project type, are not in the table. The range is a range of verified fee schedules, not a national average.
How Jurisdictions Price a Remodel Permit
The dollar figures look arbitrary until you see the formula behind each one. Every jurisdiction in the table uses one of three methods, and the method matters more than the project.
Remodel Permit Cost by Jurisdiction
Building permit fee for an interior remodel ($30,000 construction value, 300 sq ft of work area), lowest to highest. Each total is computed by PermitPrice's calculator engine from the jurisdiction's published schedule with identical inputs, so the rows are directly comparable. Click a jurisdiction for its full fee schedule and source.
| Jurisdiction | Method | Line items | All-in total | Schedule effective | Data quality |
|---|---|---|---|---|---|
| Grand Prairie, TX | Per sq ft | Building Permit Fee $75.00 | $75.00 | Sep 2, 2025 | Verified |
| Lubbock, TX | Per sq ft | Building Permit Fee $75.00 | $75.00 | Oct 1, 2025 | Verified |
| San Marcos, TX | Per sq ft | Building Permit Fee $126.00 | $126.00 | Oct 1, 2025 | Verified |
| Irving, TX | Per sq ft | Building Permit Fee $130.00 | $130.00 | Feb 13, 2026 | Verified |
| Harford County, MD | Per sq ft | Building Permit Fee $45.00 + Application Fee (non-refundable) $100.00 | $145.00 | Jan 1, 2025 | Verified |
| Norfolk City, VA | Flat fee | Building Permit Fee $100.00 + Plan Review Fee $35.00 + Processing Fee $15.00 + Virginia State Levy (2%) $2.00 | $152.00 | Jul 1, 2021 | Source-age |
| Corpus Christi, TX | Per sq ft | Building Permit Fee $146.41 + 4.5% Surcharge $6.59 | $153.00 | Oct 1, 2025 | Verified |
| Tyler, TX | Per sq ft | Building Permit Fee $141.00 + Plan Review Fee $28.20 | $169.20 | Sep 9, 2026 | Verified |
| Frederick County, MD | Flat by size tier | Building Permit Fee $137.00 + Filing Fee $33.00 + Automation Enhancement Fee $11.00 | $181.00 | Jul 1, 2026 | Verified |
| McKinney, TX | Per sq ft | Building Permit Fee $204.00 | $204.00 | Undated schedule | Verified |
| Denton, TX | Per sq ft | Building Permit Fee $96.00 + Plan Review Fee $112.00 | $208.00 | Oct 1, 2026 | Verified |
| Waco, TX | Flat fee | Building Permit Fee $200.00 + Technology Fee $15.00 | $215.00 | Undated schedule | Verified |
| Georgetown, TX | Per sq ft | Building Permit Fee $150.00 + Application Fee $60.00 + Technology Fee $10.00 | $220.00 | Oct 1, 2023 | Source-age |
| College Station, TX | Per sq ft | Building Permit Fee $225.00 | $225.00 | Oct 1, 2025 | Verified |
| Richmond City, VA | Value tiers | Building Permit Fee $232.96 + Virginia USBC State Levy $4.66 | $237.62 | Nov 18, 2013 | Source-age |
| Arlington, TX | Per sq ft | Building Permit Fee $240.00 | $240.00 | Sep 1, 2025 | Verified |
| Henrico County, VA | Value tiers | Building Permit Fee $250.00 + Virginia USBC State Levy $5.00 | $255.00 | Undated schedule | Verified |
| Virginia Beach City, VA | Value tiers | Building Permit Fee $200.00 + Plan Review Fee $100.00 + Virginia State Levy (2%) $4.00 + Technology Fee $10.00 | $314.00 | Jul 1, 2025 | Verified |
| Anne Arundel County, MD | Flat by value tier | Building Permit Fee $292.00 + Application Fee (non-refundable) $43.00 | $335.00 | Oct 1, 2024 | Verified |
| Dallas, TX | Value tiers | Building Permit Fee $388.39 | $388.39 | May 1, 2024 | Verified |
| Plano, TX | Value tiers | Building Permit Fee $400.65 | $400.65 | Nov 1, 2025 | Verified |
| Prince George's County, MD | Percent of cost | Building Permit Fee $300.00 + DPIE Administrative Fee $66.00 + DPIE Technology Fee (10%) $36.60 | $402.60 | Mar 2, 2025 | Verified |
| Loudoun County, VA | Flat fee | Building Permit Fee $395.00 + Virginia USBC State Levy $7.90 | $402.90 | Jul 1, 2022 | Source-age |
| Montgomery County, MD | Per sq ft | Building Permit Fee $235.06 + DPS Filing Fee $329.59 | $564.65 | Jul 1, 2026 | Verified |
| Fairfax County, VA | Percent of cost | Building Permit Fee $900.00 + Virginia USBC Code Academy Levy $18.00 + Fairfax County Technology Surcharge $90.00 | $1,008.00 | Jul 1, 2026 | Verified |
Verified = computed from the official fee schedule linked on the jurisdiction page. Source-age = the official schedule is dated before 2024 and may have been superseded; the jurisdiction page discloses the caveat. Undated schedule = the official source shows no printed effective date. Totals use each jurisdiction's own rounding and include only the line items shown.
What Drives the 13x Difference
The same project costs $75.00 to permit in Grand Prairie, TX and $1,008.00 in Fairfax County, VA. Four things account for almost all of that gap.
- Pricing method. A schedule that charges on project value or floor area scales with the job; a flat fee does not. That alone separates the top of the table from the bottom.
- Stacked surcharges. Virginia adds a 2% state levy on every permit. Some jurisdictions add a plan review fee, an application fee, or a technology fee. Each is a line on the invoice that a headline "permit fee" leaves out.
- Minimum fees. Where a percentage or per-square-foot rate would produce a small number, the schedule's minimum applies instead.
- Schedule age. Fee schedules are typically re-adopted each fiscal year (July 1 in Virginia and Maryland, October 1 in many Texas cities). A jurisdiction whose published schedule is several years old may charge more today than the table shows; those rows are flagged.
When These Numbers May Not Apply
- Your project cost or size differs from the example. Flat-fee rows do not change; value-based and size-based rows do. Use the jurisdiction page or the calculator with your own inputs.
- The building official substitutes a valuation. Value-based jurisdictions may replace a low declared cost with a valuation table figure, raising the permit fee.
- The schedule has been re-adopted. Rows flagged Source-age or Undated may be higher today. The jurisdiction page shows the last date PermitPrice verified the schedule.
- Work started before the permit. After-the-fact permits, reinspection fees and penalties are outside every figure on this page.
- Special districts. Historic overlays, floodplains and HOA covenants add review steps and sometimes fees that the building permit schedule does not include.
Frequently Asked Questions
-
Grand Prairie, TX official fee schedule Effective Sep 2, 2025 · Extracted Jun 24, 2026
-
Georgetown, TX official fee schedule Effective Oct 1, 2023 · Last verified Oct 3, 2026
-
Fairfax County, VA official fee schedule Effective Jul 1, 2026 · Last verified Sep 18, 2026
The remaining 22 jurisdictions in the table cite their official schedule, with effective and verified dates, on their linked pages.