Skip to main content

Pool Permit Cost in College Station, TX (2026)

Residential pool permit fees for the City of College Station, Texas (Brazos County), pulled directly from the Planning & Development Services FY26 fee schedule - updated September 29, 2025, with fees effective October 1, 2025. Unlike flat-fee cities such as Round Rock or Plano, College Station prices Pool Permits from its valuation-based permit fee schedule: $40 for the first $1,000 of declared project valuation plus $6.70 per additional $1,000 up to $50,000, then $370 for the first $50,000 plus $5.35 per $1,000 from $50,001 to $100,000. A typical $40,000 in-ground gunite pool pays a $301.30 pool permit fee - permit fee only, because electrical and plumbing trade permits are billed separately. Texas has no statewide permit levy. Fees are CPI-adjusted annually each October 1, so confirm current rates with Planning & Development Services at 979-764-3500 before budgeting.

Fee Basis
Valuation-based - $40 first $1,000 + $6.70 per additional $1,000 (to $50,000)
$40,000 In-Ground Pool
$301.30 permit fee (trade permits separate)
Electrical Trade Permit
$54 minimum (separate permit)
Reinspection Fee
$132
State / City Percentage Levy
None (Texas has no state levy)
Fee Status
FY26 official schedule - effective October 1, 2025 (CURRENT)
What This Guide Covers - and What It Does Not

This guide covers: City of College Station, Texas residential pool permit fees as published in the Planning & Development Services FY26 fee schedule (updated September 29, 2025, fees effective October 1, 2025). The Pool Permit is priced from the city's valuation-based permit fee schedule - the fee scales with the declared construction value of the pool project, not a flat per-permit rate.

Trade permits are separate: the pool permit fee does not include the Electrical Permit ($54 minimum), the Plumbing Permit ($40 base plus $6.75 per fixture), or the Plumbing Gas permit ($40 base plus $6.75 for up to four outlets, plus $1.35 for each outlet over four - relevant for gas pool heaters). A pool project typically needs the pool permit plus an electrical permit at minimum; any combined total on this page is labeled as a build-up estimate.

This guide does NOT cover: Pool contractor construction costs. HOA architectural approvals. Pool barrier and fence fees - the FY26 fee schedule does not itemize a separate residential pool-barrier permit line, so route barrier and fence questions to Planning & Development Services at 979-764-3500 rather than assuming a figure. Commercial pool projects.

Important note on fee currency: College Station CPI-adjusts its fee schedule annually each October 1. The figures on this page are from the FY26 schedule effective October 1, 2025, and will change at the next annual adjustment - confirm current rates with the department before relying on any figure for a load-bearing budget.

Key Takeaways
  • College Station prices pool permits from its valuation-based permit fee schedule, not a flat fee: $40 for the first $1,000 of valuation plus $6.70 per additional $1,000 up to $50,000, then $370 plus $5.35 per $1,000 from $50,001 to $100,000. The fee scales with the value you declare.
  • A $40,000 in-ground pool - a typical gunite starting point - pays a $301.30 pool permit fee. A $25,000 pool pays $200.80, a $60,000 pool pays $423.50, and an $85,000 pool-plus-outdoor-living project pays $557.25. All of these are the pool permit only.
  • Trade permits are separate: Electrical Permit $54 minimum, Plumbing Permit $40 base plus $6.75 per fixture, and Plumbing Gas $40 base plus $6.75 (up to four outlets) for gas pool heaters. A $40,000 pool plus the electrical minimum comes to approximately $355.30 - an estimate, since actual trade fees depend on scope.
  • Texas has no statewide percentage permit levy, and College Station adds no city surcharge on top of the schedule. A failed inspection re-visit costs $132 per reinspection.
  • For context: a $40,000 College Station pool at $301.30 sits near Plano's $300 flat in-ground fee and above Killeen's $255 - but unlike those flat-fee cities, the College Station fee keeps rising as the project value rises.
  • The FY26 fee schedule does not itemize a separate residential pool-barrier permit line. Barrier and fence requirements still apply - route those questions to Planning & Development Services at 979-764-3500.
  • Fees are CPI-adjusted annually each October 1. The figures here are from the FY26 schedule (updated September 29, 2025, effective October 1, 2025) and will change at the next adjustment.

College Station Pool Permit Fee Structure

College Station prices Pool Permits from the city's valuation-based permit fee schedule. There is no flat pool-permit line - the declared construction value of the project sets the fee, and electrical and plumbing trade work is permitted and billed separately.

Item Permit Fee How It Is Calculated
Valuation $1,000 or less $40.00 Base fee for the first $1,000 of declared project valuation.
Valuation $1,001 - $50,000 $40 + $6.70 per additional $1,000 $40 for the first $1,000 plus $6.70 per additional $1,000 (or fraction) up to $50,000.
Valuation $50,001 - $100,000 $370 + $5.35 per additional $1,000 $370 for the first $50,000 plus $5.35 per $1,000 from $50,001 to $100,000.
Valuation $100,001 - $500,000 $640 + $4.00 per additional $1,000 $640 for the first $100,000 plus $4.00 per $1,000 from $100,001 to $500,000.
Valuation over $500,000 $2,255 + $2.70 per additional $1,000 $2,255 for the first $500,000 plus $2.70 per $1,000 thereafter.
Electrical Permit (separate) $54 minimum Covers the first 1,000 sq ft plus $0.03 per sq ft over. Pool equipment, bonding, and lighting circuits require it - not included in the pool permit.
Plumbing Permit (separate) $40 base + $6.75 per fixture Separate trade permit when plumbing fixtures are in scope.
Plumbing Gas permit (separate) $40 base + $6.75 (up to 4 outlets) Plus $1.35 for each outlet over four. Relevant when the project includes a gas pool heater.
Reinspection $132.00 Charged per reinspection when an inspection fails and must be repeated.
State / city percentage levy None Texas has no statewide permit levy; College Station adds no city surcharge.

Source: City of College Station Planning & Development Services FY26 Fee Schedule - updated September 29, 2025, fees effective October 1, 2025. The schedule is CPI-adjusted annually each October 1, so these figures will change at the next adjustment. Confirm current rates with Planning & Development Services at 979-764-3500 before filing.

Worked Examples - Real Pool Projects in College Station

Each example applies the valuation formula exactly as published. Every figure below is the pool permit fee only - electrical, plumbing, and gas trade permits are separate line items, and any combined total is labeled as a build-up estimate.

Example 1: $25,000 pool

A homeowner installs a $25,000 pool - for example a smaller fiberglass or vinyl-liner project. The valuation sits in the $1,001 - $50,000 bracket.

  • First $1,000 of valuation: $40.00
  • Additional 24 x $1,000 at $6.70 each: $160.80
  • Texas state levy: $0.00 (none)
  • Pool permit fee: $200.80

Permit fee only - the electrical trade permit ($54 minimum) and any plumbing permits are billed separately.

Example 2: $40,000 in-ground pool (typical gunite starting point)

A homeowner builds a $40,000 in-ground gunite pool - a common entry point for gunite construction in the region. The valuation stays inside the $1,001 - $50,000 bracket.

  • First $1,000 of valuation: $40.00
  • Additional 39 x $1,000 at $6.70 each: $261.30
  • Texas state levy: $0.00 (none)
  • Pool permit fee: $301.30

Build-up estimate with trades: adding the electrical permit at its $54 minimum brings the project to approximately $355.30 - an ESTIMATE, because the actual electrical fee depends on the scope and a gas heater would add a plumbing gas permit on top.

Example 3: $60,000 pool

A homeowner builds a $60,000 pool. The valuation crosses into the $50,001 - $100,000 bracket, where the marginal rate drops from $6.70 to $5.35 per $1,000.

  • First $50,000 of valuation: $370.00
  • Additional 10 x $1,000 at $5.35 each: $53.50
  • Texas state levy: $0.00 (none)
  • Pool permit fee: $423.50

Permit fee only - trade permits separate.

Example 4: $85,000 pool + outdoor living project

A homeowner combines a pool with outdoor living work for a declared valuation of $85,000, staying in the $50,001 - $100,000 bracket.

  • First $50,000 of valuation: $370.00
  • Additional 35 x $1,000 at $5.35 each: $187.25
  • Texas state levy: $0.00 (none)
  • Pool permit fee: $557.25

Permit fee only - a project of this scope will typically also carry the electrical permit and, with a gas heater or outdoor kitchen gas line, the plumbing gas permit ($40 base plus $6.75 for up to four outlets, plus $1.35 each over four). Confirm how PDS wants combined pool-plus-outdoor-living scopes valued and permitted before filing.

When This Estimate May Not Apply

The valuation formula covers the standard residential pool permit case published in the FY26 fee schedule. Route your project to Planning & Development Services at 979-764-3500 before relying on these figures if any of the following applies:

  • Your declared valuation differs from these examples. The fee scales with the construction value you declare - a $30,000 pool and a $70,000 pool pay different fees under the same formula. Recompute from the schedule, or use the department's own figure.
  • The project includes trade work. Almost every pool needs an electrical permit ($54 minimum) for pump, bonding, and lighting circuits, and a gas heater adds a plumbing gas permit. Those fees are on top of every pool permit figure on this page.
  • You have pool barrier or fence questions. The FY26 fee schedule does not itemize a separate residential pool-barrier permit line. Barrier requirements still apply to pools - ask PDS how barrier and fence work is permitted and priced for your project rather than assuming it is free or bundled.
  • You are budgeting for impact fees. Impact fees do not apply to a standalone pool permit, but verify the scope classification with PDS if your project bundles the pool with other construction.
  • Inspections fail. Each reinspection is $132 on top of the permit fees.
  • You are reading this after the next October 1. College Station CPI-adjusts its fee schedule annually each October 1. The FY26 figures here took effect October 1, 2025, and will change at the next adjustment.

Every figure on this page is an educational estimate built from the published schedule - the fee PDS quotes at application time is the official number.

College Station Pool Permit Cost vs Other Verified Jurisdictions

Most nearby Texas cities publish flat pool permit fees, which makes College Station's valuation formula the outlier - read the basis column carefully, because a flat fee and a scaling fee only match at one project value.

Jurisdiction Pool Fee Basis Typical Pool Permit
College Station, TX - $40,000 in-ground pool Valuation formula ($40 + $6.70/$1,000) $301.30
Plano, TX Flat: $300 in-ground / $55 above-ground / $150 in-ground spa (Ord 2025-11-4) $300.00 in-ground
Round Rock, TX Flat: $350 in-ground / $125 above-ground or spa (dept pages, undated) $350.00 in-ground
Killeen, TX Flat: $245 + $10 tech fee below-ground / $80 + $10 above-ground (FY2026) $255.00 below-ground
Austin, TX No flat pool line - small-projects review $132.86 + standalone inspections No flat total published

A $40,000 College Station pool at $301.30 sits near Plano's $300 flat in-ground fee and above Killeen's $255 - but the comparison is decision-relevant in the other direction too: unlike the flat-fee cities, the College Station fee keeps scaling with project value, so a $60,000 pool pays $423.50 here while Plano would still charge $300. Austin does not publish a flat pool permit line - it prices a small-projects review at $132.86 plus standalone inspections, so no single Austin figure is directly comparable. Round Rock's pool fees come from current department pages that carry no printed date.

Side-by-Side Math

See how College Station compares head-to-head against Austin across project types.

Frequently Asked Questions

College Station prices pool permits by project valuation: $40 for the first $1,000 plus $6.70 per additional $1,000 up to $50,000, then $370 for the first $50,000 plus $5.35 per $1,000 to $100,000. A $25,000 pool pays $200.80, a $40,000 in-ground pool pays $301.30, and a $60,000 pool pays $423.50 - pool permit only, with electrical and plumbing trade permits billed separately. Figures are from the FY26 schedule effective October 1, 2025; confirm current rates at 979-764-3500.
No. Unlike Round Rock ($350 flat in-ground) or Plano ($300 flat in-ground), College Station prices Pool Permits from its valuation-based permit fee schedule - the fee scales with the declared construction value of the project. A $40,000 pool pays $301.30 while a $60,000 pool pays $423.50 under the same formula.
No. Trade permits are separate line items: the Electrical Permit is $54 minimum (covering the first 1,000 sq ft plus $0.03 per sq ft over), the Plumbing Permit is $40 base plus $6.75 per fixture, and the Plumbing Gas permit is $40 base plus $6.75 for up to four outlets plus $1.35 each over four. A pool project typically needs the pool permit plus an electrical permit at minimum.
A gas pool heater brings the Plumbing Gas permit into scope: $40 base plus $6.75 for up to four outlets, plus $1.35 for each outlet over four. That is on top of the valuation-based pool permit and the electrical permit. Any combined total is a build-up estimate - the exact trade fees depend on your project's scope, so confirm with PDS at 979-764-3500.
The FY26 fee schedule does not itemize a separate residential pool-barrier permit line, so we do not publish a barrier fee. Pool barrier requirements still apply to residential pools - route barrier and fence questions to Planning & Development Services at 979-764-3500 or cspds@cstx.gov to learn how that work is permitted and priced for your project.
Impact fees do not apply to a standalone pool permit. If your pool is bundled with other construction - an addition, a new outdoor structure, or a larger remodel - verify the scope classification with PDS at 979-764-3500 before assuming the impact-fee exclusion holds for the whole project.
At a $40,000 valuation, College Station's $301.30 sits near Plano's $300 flat in-ground fee, below Round Rock's $350, and above Killeen's $255 ($245 plus a $10 technology fee). The structural difference matters more than the snapshot: those cities charge the same flat fee at any project value, while College Station's fee keeps scaling - a $60,000 pool pays $423.50 here. Austin publishes no flat pool line at all (small-projects review $132.86 plus standalone inspections), so it is not directly comparable.
The figures come from the City of College Station Planning & Development Services FY26 Fee Schedule, updated September 29, 2025, with fees effective October 1, 2025 - the current schedule. College Station CPI-adjusts its fees annually each October 1, so these numbers will change at the next adjustment. Applications go through the eTRAKiT portal, and current rates can be confirmed at 979-764-3500 or cspds@cstx.gov.

Who to Contact

Department City of College Station - Planning & Development Services
Phone 979-764-3500 (8 a.m. - 5 p.m. weekdays)
Email cspds@cstx.gov
Address 1101 Texas Ave., College Station, TX 77840
Online permit portal eTRAKiT (cd.cstx.gov/eTRAKiT)

Sources

Official Sources - Recorded July 2026
Next Step

Confirm your specific College Station pool permit cost or compare against Austin.

Always verify current pool permit fees directly with College Station Planning & Development Services before budgeting or filing. The figures on this page come from the FY26 fee schedule effective October 1, 2025, and College Station CPI-adjusts its fees annually each October 1. Call 979-764-3500 (8 a.m. - 5 p.m. weekdays), email cspds@cstx.gov, or apply through the eTRAKiT portal at cd.cstx.gov/eTRAKiT to confirm the current pool permit and trade permit rates before submitting an application.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by City of College Station Planning & Development Services at the time of application. The pool permit fee is valuation-based and scales with the construction value you declare; trade permits (electrical, plumbing, plumbing gas) are separate, and any combined totals on this page are labeled build-up estimates. Fee schedules are CPI-adjusted annually each October 1 and can change without notice - verify with Planning & Development Services (979-764-3500) before relying on any figure. Contractor costs, HOA approvals, pool barrier and fence fees (not itemized in the FY26 schedule), and commercial pool projects are excluded from the figures on this page.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.