Pool Permit Cost in College Station, TX (2026)
Residential pool permit fees for the City of College Station, Texas (Brazos County), pulled directly from the Planning & Development Services FY26 fee schedule - updated September 29, 2025, with fees effective October 1, 2025. Unlike flat-fee cities such as Round Rock or Plano, College Station prices Pool Permits from its valuation-based permit fee schedule: $40 for the first $1,000 of declared project valuation plus $6.70 per additional $1,000 up to $50,000, then $370 for the first $50,000 plus $5.35 per $1,000 from $50,001 to $100,000. A typical $40,000 in-ground gunite pool pays a $301.30 pool permit fee - permit fee only, because electrical and plumbing trade permits are billed separately. Texas has no statewide permit levy. Fees are CPI-adjusted annually each October 1, so confirm current rates with Planning & Development Services at 979-764-3500 before budgeting.
This guide covers: City of College Station, Texas residential pool permit fees as published in the Planning & Development Services FY26 fee schedule (updated September 29, 2025, fees effective October 1, 2025). The Pool Permit is priced from the city's valuation-based permit fee schedule - the fee scales with the declared construction value of the pool project, not a flat per-permit rate.
Trade permits are separate: the pool permit fee does not include the Electrical Permit ($54 minimum), the Plumbing Permit ($40 base plus $6.75 per fixture), or the Plumbing Gas permit ($40 base plus $6.75 for up to four outlets, plus $1.35 for each outlet over four - relevant for gas pool heaters). A pool project typically needs the pool permit plus an electrical permit at minimum; any combined total on this page is labeled as a build-up estimate.
This guide does NOT cover: Pool contractor construction costs. HOA architectural approvals. Pool barrier and fence fees - the FY26 fee schedule does not itemize a separate residential pool-barrier permit line, so route barrier and fence questions to Planning & Development Services at 979-764-3500 rather than assuming a figure. Commercial pool projects.
Important note on fee currency: College Station CPI-adjusts its fee schedule annually each October 1. The figures on this page are from the FY26 schedule effective October 1, 2025, and will change at the next annual adjustment - confirm current rates with the department before relying on any figure for a load-bearing budget.
A College Station, TX pool permit is priced by project valuation: $40 for the first $1,000 plus $6.70 per additional $1,000 up to $50,000, then $370 for the first $50,000 plus $5.35 per $1,000 to $100,000. A $25,000 pool pays $200.80, a $40,000 in-ground pool pays $301.30, and a $60,000 pool pays $423.50 - permit fee only, with electrical (from $54) and plumbing trade permits billed separately. Figures are from the FY26 fee schedule effective October 1, 2025; confirm current rates with Planning & Development Services at 979-764-3500.
- College Station prices pool permits from its valuation-based permit fee schedule, not a flat fee: $40 for the first $1,000 of valuation plus $6.70 per additional $1,000 up to $50,000, then $370 plus $5.35 per $1,000 from $50,001 to $100,000. The fee scales with the value you declare.
- A $40,000 in-ground pool - a typical gunite starting point - pays a $301.30 pool permit fee. A $25,000 pool pays $200.80, a $60,000 pool pays $423.50, and an $85,000 pool-plus-outdoor-living project pays $557.25. All of these are the pool permit only.
- Trade permits are separate: Electrical Permit $54 minimum, Plumbing Permit $40 base plus $6.75 per fixture, and Plumbing Gas $40 base plus $6.75 (up to four outlets) for gas pool heaters. A $40,000 pool plus the electrical minimum comes to approximately $355.30 - an estimate, since actual trade fees depend on scope.
- Texas has no statewide percentage permit levy, and College Station adds no city surcharge on top of the schedule. A failed inspection re-visit costs $132 per reinspection.
- For context: a $40,000 College Station pool at $301.30 sits near Plano's $300 flat in-ground fee and above Killeen's $255 - but unlike those flat-fee cities, the College Station fee keeps rising as the project value rises.
- The FY26 fee schedule does not itemize a separate residential pool-barrier permit line. Barrier and fence requirements still apply - route those questions to Planning & Development Services at 979-764-3500.
- Fees are CPI-adjusted annually each October 1. The figures here are from the FY26 schedule (updated September 29, 2025, effective October 1, 2025) and will change at the next adjustment.
College Station Pool Permit Fee Structure
College Station prices Pool Permits from the city's valuation-based permit fee schedule. There is no flat pool-permit line - the declared construction value of the project sets the fee, and electrical and plumbing trade work is permitted and billed separately.
| Item | Permit Fee | How It Is Calculated |
|---|---|---|
| Valuation $1,000 or less | $40.00 | Base fee for the first $1,000 of declared project valuation. |
| Valuation $1,001 - $50,000 | $40 + $6.70 per additional $1,000 | $40 for the first $1,000 plus $6.70 per additional $1,000 (or fraction) up to $50,000. |
| Valuation $50,001 - $100,000 | $370 + $5.35 per additional $1,000 | $370 for the first $50,000 plus $5.35 per $1,000 from $50,001 to $100,000. |
| Valuation $100,001 - $500,000 | $640 + $4.00 per additional $1,000 | $640 for the first $100,000 plus $4.00 per $1,000 from $100,001 to $500,000. |
| Valuation over $500,000 | $2,255 + $2.70 per additional $1,000 | $2,255 for the first $500,000 plus $2.70 per $1,000 thereafter. |
| Electrical Permit (separate) | $54 minimum | Covers the first 1,000 sq ft plus $0.03 per sq ft over. Pool equipment, bonding, and lighting circuits require it - not included in the pool permit. |
| Plumbing Permit (separate) | $40 base + $6.75 per fixture | Separate trade permit when plumbing fixtures are in scope. |
| Plumbing Gas permit (separate) | $40 base + $6.75 (up to 4 outlets) | Plus $1.35 for each outlet over four. Relevant when the project includes a gas pool heater. |
| Reinspection | $132.00 | Charged per reinspection when an inspection fails and must be repeated. |
| State / city percentage levy | None | Texas has no statewide permit levy; College Station adds no city surcharge. |
Source: City of College Station Planning & Development Services FY26 Fee Schedule - updated September 29, 2025, fees effective October 1, 2025. The schedule is CPI-adjusted annually each October 1, so these figures will change at the next adjustment. Confirm current rates with Planning & Development Services at 979-764-3500 before filing.
Worked Examples - Real Pool Projects in College Station
Each example applies the valuation formula exactly as published. Every figure below is the pool permit fee only - electrical, plumbing, and gas trade permits are separate line items, and any combined total is labeled as a build-up estimate.
A homeowner installs a $25,000 pool - for example a smaller fiberglass or vinyl-liner project. The valuation sits in the $1,001 - $50,000 bracket.
- First $1,000 of valuation: $40.00
- Additional 24 x $1,000 at $6.70 each: $160.80
- Texas state levy: $0.00 (none)
- Pool permit fee: $200.80
Permit fee only - the electrical trade permit ($54 minimum) and any plumbing permits are billed separately.
A homeowner builds a $40,000 in-ground gunite pool - a common entry point for gunite construction in the region. The valuation stays inside the $1,001 - $50,000 bracket.
- First $1,000 of valuation: $40.00
- Additional 39 x $1,000 at $6.70 each: $261.30
- Texas state levy: $0.00 (none)
- Pool permit fee: $301.30
Build-up estimate with trades: adding the electrical permit at its $54 minimum brings the project to approximately $355.30 - an ESTIMATE, because the actual electrical fee depends on the scope and a gas heater would add a plumbing gas permit on top.
A homeowner builds a $60,000 pool. The valuation crosses into the $50,001 - $100,000 bracket, where the marginal rate drops from $6.70 to $5.35 per $1,000.
- First $50,000 of valuation: $370.00
- Additional 10 x $1,000 at $5.35 each: $53.50
- Texas state levy: $0.00 (none)
- Pool permit fee: $423.50
Permit fee only - trade permits separate.
A homeowner combines a pool with outdoor living work for a declared valuation of $85,000, staying in the $50,001 - $100,000 bracket.
- First $50,000 of valuation: $370.00
- Additional 35 x $1,000 at $5.35 each: $187.25
- Texas state levy: $0.00 (none)
- Pool permit fee: $557.25
Permit fee only - a project of this scope will typically also carry the electrical permit and, with a gas heater or outdoor kitchen gas line, the plumbing gas permit ($40 base plus $6.75 for up to four outlets, plus $1.35 each over four). Confirm how PDS wants combined pool-plus-outdoor-living scopes valued and permitted before filing.
When This Estimate May Not Apply
The valuation formula covers the standard residential pool permit case published in the FY26 fee schedule. Route your project to Planning & Development Services at 979-764-3500 before relying on these figures if any of the following applies:
- Your declared valuation differs from these examples. The fee scales with the construction value you declare - a $30,000 pool and a $70,000 pool pay different fees under the same formula. Recompute from the schedule, or use the department's own figure.
- The project includes trade work. Almost every pool needs an electrical permit ($54 minimum) for pump, bonding, and lighting circuits, and a gas heater adds a plumbing gas permit. Those fees are on top of every pool permit figure on this page.
- You have pool barrier or fence questions. The FY26 fee schedule does not itemize a separate residential pool-barrier permit line. Barrier requirements still apply to pools - ask PDS how barrier and fence work is permitted and priced for your project rather than assuming it is free or bundled.
- You are budgeting for impact fees. Impact fees do not apply to a standalone pool permit, but verify the scope classification with PDS if your project bundles the pool with other construction.
- Inspections fail. Each reinspection is $132 on top of the permit fees.
- You are reading this after the next October 1. College Station CPI-adjusts its fee schedule annually each October 1. The FY26 figures here took effect October 1, 2025, and will change at the next adjustment.
Every figure on this page is an educational estimate built from the published schedule - the fee PDS quotes at application time is the official number.
College Station Pool Permit Cost vs Other Verified Jurisdictions
Most nearby Texas cities publish flat pool permit fees, which makes College Station's valuation formula the outlier - read the basis column carefully, because a flat fee and a scaling fee only match at one project value.
| Jurisdiction | Pool Fee Basis | Typical Pool Permit |
|---|---|---|
| College Station, TX - $40,000 in-ground pool | Valuation formula ($40 + $6.70/$1,000) | $301.30 |
| Plano, TX | Flat: $300 in-ground / $55 above-ground / $150 in-ground spa (Ord 2025-11-4) | $300.00 in-ground |
| Round Rock, TX | Flat: $350 in-ground / $125 above-ground or spa (dept pages, undated) | $350.00 in-ground |
| Killeen, TX | Flat: $245 + $10 tech fee below-ground / $80 + $10 above-ground (FY2026) | $255.00 below-ground |
| Austin, TX | No flat pool line - small-projects review $132.86 + standalone inspections | No flat total published |
A $40,000 College Station pool at $301.30 sits near Plano's $300 flat in-ground fee and above Killeen's $255 - but the comparison is decision-relevant in the other direction too: unlike the flat-fee cities, the College Station fee keeps scaling with project value, so a $60,000 pool pays $423.50 here while Plano would still charge $300. Austin does not publish a flat pool permit line - it prices a small-projects review at $132.86 plus standalone inspections, so no single Austin figure is directly comparable. Round Rock's pool fees come from current department pages that carry no printed date.
See how College Station compares head-to-head against Austin across project types.
Frequently Asked Questions
Who to Contact
| Department | City of College Station - Planning & Development Services |
| Phone | 979-764-3500 (8 a.m. - 5 p.m. weekdays) |
| cspds@cstx.gov | |
| Address | 1101 Texas Ave., College Station, TX 77840 |
| Online permit portal | eTRAKiT (cd.cstx.gov/eTRAKiT) |
Sources
-
City of College Station - Planning & Development Services FY26 Fee Schedule (PDF) Updated September 29, 2025 - fees effective October 1, 2025 - College Station, TX - Primary source for the valuation-based permit fee schedule ($40 first $1,000 + $6.70 per additional $1,000 to $50,000; $370 + $5.35 to $100,000; $640 + $4.00 to $500,000; $2,255 + $2.70 thereafter), electrical / plumbing / plumbing gas trade permit fees, and the $132 reinspection fee current - FY26
-
City of College Station - Planning & Development Services department page Retrieved July 2026 - College Station, TX - Department contact information, permitting process, and the eTRAKiT online permit portal
Confirm your specific College Station pool permit cost or compare against Austin.