Howard County vs Montgomery County, MD Building Permit Fees (2026)

Howard County and Montgomery County both price residential new construction and additions per square foot, with no statewide Maryland levy - but the rates and the add-ons differ sharply. Howard charges $0.25 per square foot plus a 10% technology fee and low flat filing fees; Montgomery charges $0.767865 per square foot with large filing-fee floors and no technology fee. Across every comparable project, Howard County comes out lower.

Key Takeaways
  • Both counties price new construction and additions per square foot, but Howard is $0.25/sq ft and Montgomery is $0.767865/sq ft - about three times higher.
  • Howard adds a 10% technology fee and small flat filing fees ($25-$100); Montgomery has no technology fee but large filing-fee floors ($286.60 additions/alterations, $757.05 new homes).
  • A 400 sq ft addition: $160 in Howard vs $593.75 in Montgomery.
  • A new 2,400 sq ft house (building-permit side): $810 in Howard vs $2,764.32 in Montgomery.
  • Neither county adds a statewide percentage levy; both assess large separate impact/school charges on new homes that are excluded here.
  • Montgomery prices alterations per square foot ($0.681345/sq ft); Howard uses flat alteration fees ($50 up to 200 sq ft, $100 over).

Howard vs Montgomery: Fee Structure Side by Side

Fee Element Howard County (DILP) Montgomery County (DPS)
New SF construction / addition rate $0.25 / sq ft $0.767865 / sq ft
Alteration / repair Flat: $50 (≤200 sq ft) or $100 (over) $0.681345 / sq ft
Filing fee $25 alteration, $50 addition, $100 new residential 50% of permit or $286.60 (addition/alteration); 50% or $757.05 (new home)
Technology fee 10% of permit fee None
State levy None (Maryland) None (Maryland)
Deck Priced as addition/structure per sq ft Flat $194.67 (≤500 sq ft)
Fee schedule effective July 1, 2025 (FY2026) Printed FY2022 (verify current)

Shared-Assumption Worked Examples

Each example assumes the same square footage for both counties.

Example 1: Room Addition, 400 sq ft

Fee Component Howard County Montgomery County
Building permit fee 400 × $0.25 = $100.00 400 × $0.767865 = $307.15
Filing fee $50.00 $286.60 (floor)
Technology fee (10%) $10.00 $0.00
Total $160.00 $593.75

Note: Same 400 sq ft addition. Montgomery's filing-fee floor of $286.60 and higher per-sq-ft rate make it about 3.7x Howard. Howard's 10% technology fee applies to the $100 permit fee.

Example 2: New Detached House, 2,400 sq ft

Fee Component Howard County Montgomery County
Building permit fee 2,400 × $0.25 = $600.00 2,400 × $0.767865 = $1,842.88
Filing fee $100.00 $921.44 (50% of permit)
Technology fee (10%) $60.00 $0.00
MD Home Builder Guaranty Fund $50.00 (not itemized here)
Total (building-permit side) $810.00 $2,764.32

Note: Building-permit side only. Both counties assess large separate impact, excise, and school facility charges on new homes, excluded here. Montgomery is about 3.4x Howard at this size.

Example 3: Remodel, 200 sq ft (alteration)

Fee Component Howard County Montgomery County
Building permit fee Flat $50.00 (≤200 sq ft) 200 × $0.681345 = $136.27
Filing fee $25.00 $286.60 (floor)
Technology fee (10%) $5.00 $0.00
Total $80.00 $422.87

Note: Howard prices alterations as a flat fee by area; Montgomery per square foot, but Montgomery's $286.60 filing-fee floor dominates a small remodel. Assumes 200 sq ft of altered area.

Which County Is Cheaper for Your Project?

Scenario Lower Fee Why
Small remodel (under 200 sq ft) Howard ($80 vs $422.87) Montgomery's filing-fee floor dominates small jobs
Room addition Howard ($160 vs $593.75) Howard's $0.25/sq ft is far below Montgomery's $0.767865
New detached house Howard ($810 vs $2,764) Lower per-sq-ft rate and smaller filing fee
Deck Depends on size; Montgomery flat $194.67 (≤500 sq ft) Howard prices a deck per sq ft as a structure/addition
Predictability Montgomery for flat-fee items (deck/pool/fence) Montgomery publishes flat fees for those project types

Practitioner Insight

The headline is simple - Howard County is cheaper than Montgomery County on essentially every per-square-foot project, often by three to four times, because its base rate is $0.25/sq ft against Montgomery's $0.767865 and its filing fees are a fraction of Montgomery's floors. Montgomery's one structural advantage is the published flat fee for discrete projects like decks ($194.67) and pools, which removes square-footage math. For both counties, the building permit fee is only the county's slice; the separate impact, excise, and school facility charges on a new home dwarf it. Confirm Montgomery's current rates given its FY2022 printed schedule, and Howard's at 410-313-2455.

Frequently Asked Questions

Howard County is lower on every per-square-foot project we compared. A 400 sq ft addition is $160 in Howard vs $593.75 in Montgomery; a new 2,400 sq ft house is $810 vs $2,764.32. Montgomery's higher per-square-foot rate and large filing-fee floors drive the difference.
For new construction and additions, yes - Howard at $0.25/sq ft and Montgomery at $0.767865/sq ft. They differ on alterations: Howard uses flat fees ($50/$100 by area) while Montgomery prices alterations at $0.681345/sq ft.
Howard adds a 10% technology fee on the permit fee; Montgomery does not. Neither county adds a statewide Maryland levy - Maryland has no equivalent of Virginia's 2% USBC levy.
Both Howard and Montgomery assess large separate charges on new construction - impact and excise taxes and school facility payments - that are set under their own rules and excluded from the building-permit figures here. They can exceed the permit fee many times over.
Howard County's fee schedule is effective July 1, 2025 (FY2026). Montgomery County's published DPS schedule carries a printed FY2022 effective date, so confirm current Montgomery rates before relying on them. See the Howard County and Montgomery County pages for full detail.

Sources

Official Sources
Next Step

See each county's full fee page, or compare more Maryland jurisdictions.

Verify current fees with each county before budgeting or filing. Howard County DILP: 410-313-2455. Montgomery County DPS: 240-777-0311 (FY2022 printed schedule - confirm current rates).