Shed Permit Cost in Harford County, MD (2026)

Residential shed (accessory structure) building permit fees in Harford County, Maryland, pulled directly from the official Harford County Department of Inspections, Licenses and Permits (DILP) Fee Schedule. A shed of 200 square feet and under is a flat $20 - and at that size the schedule states no certificate of occupancy or inspection is required. Over 200 SF, the fee becomes $0.15 per square foot plus a $100 non-refundable application fee. A common 12x16 (192 SF) shed permit is $20. Maryland has no statewide percentage levy and Harford adds no technology fee.

Shed 200 SF and Under
$20 flat
CO / Inspection at 200 SF and Under
None required (per the schedule)
Shed Over 200 SF
$0.15/SF + $100 application fee
State / Local Percentage Levy
None (Maryland has no statewide levy)
Technology Fee
None in Harford County
Fee Status
Official DILP fee schedule (eff. Jan 1, 2025)
What This Guide Covers - and What It Does Not

This guide covers: Harford County, Maryland residential shed and accessory structure (1-2 family) building permit fees as published in the DILP Fee Schedule (Bill 24-013): the flat $20 fee at 200 SF and under, and the $0.15/SF + $100 application-fee formula over 200 SF.

This guide does NOT cover: Trade permits (electrical for shed power, plumbing) - those are separate DILP schedules with their own fees. Zoning, setback, lot-coverage, and floodplain rules - those are set by county code, not the fee schedule. HOA approvals and shed purchase or construction costs are also excluded.

Important note: The fee here is the building permit charge only. Confirm with DILP whether your shed needs a permit and what placement rules apply before you build.

Key Takeaways
  • A shed of 200 SF and under is a flat $20 - that covers the most common backyard sizes: 8x10 (80 SF), 10x12 (120 SF), and 12x16 (192 SF) are all $20.
  • At 200 SF and under, the fee schedule states no certificate of occupancy or inspection is required for the accessory structure.
  • Over 200 SF, the formula switches to $0.15 per square foot plus a $100 non-refundable application fee: a 16x20 (320 SF) shed is $148, a 24x24 (576 SF) garage-size structure is $186.40.
  • Maryland has no statewide percentage building-permit levy and Harford adds no technology fee. The $50 MHIC fee on this schedule applies to new home permits only - not sheds.
  • Running power or water to the shed needs separate electrical or plumbing permits under DILP's trade schedules - those fees are not included here.
  • The $20 fee does not decide where the shed can go. Setback, lot-coverage, and floodplain rules are set by county code separately - confirm with DILP, like with the county's $20 fence permit.

Harford County Shed Permit Fee Structure

Harford County prices sheds under the accessory structure (1-2 family) line. 200 square feet is the break point: at or under it, a flat $20; over it, the standard residential per-square-foot formula with the $100 application fee. There is no percentage levy and no technology fee.

Shed Size Building Permit Fee Notes
200 SF and under $20.00 Flat fee. The schedule states no certificate of occupancy or inspection is required at this size.
Over 200 SF $0.15/SF + $100 $0.15 per square foot plus the $100 non-refundable application fee.
Square-footage basis Enclosed usable areas The per-SF residential basis counts enclosed usable areas (basements included); attic/storage areas under 88-inch ceilings are excluded.
State / local percentage levy None Maryland has no statewide USBC-style percentage levy. No 2% add-on, no technology fee. The $50 MHIC fee applies to new home permits only - not sheds.
Trade permits (electric / plumbing) Separate schedules Running power or water to the shed requires separate DILP trade permits, not included in the figures above.

Source: Harford County DILP Fee Schedule (Bill 24-013), accessory structure (1-2 family) lines, p. 1. Effective January 1, 2025. Whether a permit is required, and the setback, lot-coverage, and floodplain rules, are set by county code separately from the fee - confirm with DILP before filing.

Worked Examples - Real Shed Projects in Harford County

Each example uses the DILP accessory structure fee lines. At 200 SF and under the fee is the flat $20; over 200 SF every square foot is billed at $0.15 and the $100 application fee is added.

Example 1: 12x16 backyard shed (192 SF)

A homeowner installs a popular 12x16 storage shed - one of the largest sizes that still fits under the 200 SF line.

  • Shed area: 12 × 16 = 192 SF (200 SF and under)
  • Flat fee: $20.00
  • Application fee: $0.00 (the $100 application fee applies only over 200 SF)
  • Maryland percentage levy: $0.00 (none)
  • Building permit total: $20.00

An 8x10 (80 SF) or 10x12 (120 SF) shed is the same flat $20, and even a structure of exactly 200 SF stays at $20. Per the schedule, no certificate of occupancy or inspection is required at this size.

Example 2: 16x20 workshop shed (320 SF)

A homeowner builds a 16x20 workshop shed - over the 200 SF line, so the per-square-foot formula applies.

  • Shed area: 16 × 20 = 320 SF (over 200 SF)
  • Per-SF fee: 320 SF × $0.15 = $48.00
  • Non-refundable application fee: $100.00
  • Maryland percentage levy: $0.00 (none)
  • Building permit total: $148.00

A slightly smaller 14x20 (280 SF) shed is $42 + $100 = $142, and a 20x20 (400 SF) is $60 + $100 = $160. The $100 application fee is the larger share of the bill at these sizes.

Example 3: 24x24 garage-size accessory structure (576 SF)

A homeowner puts up a 24x24 detached garage-size accessory structure on a larger lot.

  • Structure area: 24 × 24 = 576 SF (over 200 SF)
  • Per-SF fee: 576 SF × $0.15 = $86.40
  • Non-refundable application fee: $100.00
  • Maryland percentage levy: $0.00 (none)
  • Building permit total: $186.40

Even a 1,000 SF accessory structure is only $150 + $100 = $250 on the building permit side. Electrical service to the structure is a separate trade permit, and setback and zoning rules still apply - confirm with DILP.

Harford County Shed Permit Cost vs Other Verified Jurisdictions

Harford's $20 flat fee at 200 SF and under is one of the cheapest verified shed permits - but the structure differs sharply across jurisdictions. Chesterfield County, VA skips the permit entirely for small sheds, while Harford still requires one (a cheap one). Read the basis column carefully.

Jurisdiction Shed Permit Basis Typical Small Shed (under 200 SF)
Harford County, MD $20 flat at 200 SF and under; $0.15/SF + $100 over $20
Chesterfield County, VA No permit at 256 SF and under; $116.28 (257-400 SF); $290.70 (over 400 SF) $0 (no permit required)
Baltimore County, MD $85 accessory structure up to 1,000 SF (2018 schedule) $85

The structural contrast matters more than the dollar gap: Chesterfield County requires no permit at all for sheds of 256 SF and under (FY2025-2026 schedule), while Harford still requires a permit for the same shed - it just costs $20. Baltimore County's $85 accessory-structure fee comes from a 2018 schedule, so treat its age accordingly. Always confirm whether a permit is required, and the zoning rules, with the local department before building.

Related Harford Permits

Planning more than a shed? See the rest of Harford County's residential permit fees.

Frequently Asked Questions

Yes - the DILP fee schedule prices an accessory structure of 200 SF and under at a flat $20, which means Harford County still issues a permit even for small sheds. That differs from places like Chesterfield County, VA, where sheds of 256 SF and under need no permit at all. Confirm the permit requirement for your specific shed with DILP at 410-638-3122 before you build.
Over 200 SF, the fee switches from the flat $20 to the standard residential formula: $0.15 per square foot plus a $100 non-refundable application fee. A 14x20 (280 SF) shed is $42 + $100 = $142; a 16x20 (320 SF) is $148; a 20x20 (400 SF) is $160; a 24x24 (576 SF) is $186.40. The jump at the 200 SF line is real - 192 SF costs $20 while 280 SF costs $142.
If you run power, lighting, or water to the shed, yes - electrical and plumbing work fall under separate DILP trade permit schedules with their own fees, which are not included in the $20 or per-SF figures on this page. A bare storage shed with no utilities needs only the building permit. Ask DILP at 410-638-3122 which trade permits your project triggers.
Not at 200 SF and under, per the fee schedule: the $20 accessory structure line states that no certificate of occupancy or inspection is required at that size. Over 200 SF, the structure is billed under the standard per-SF residential formula; ask DILP what inspections apply to your specific project.
Setback, lot-coverage, and floodplain rules are set by county code and zoning - they are not on the fee schedule and are not covered by this guide. Before placing the shed, confirm the rules for your property with DILP at 410-638-3122 or through the county permits portal at harfordcountymd.gov/985/Permits.

Sources

Official Sources - Recorded June 2026
Next Step

Confirm your specific Harford shed permit cost or see the rest of the county's fees.

Always verify current shed permit fees and rules directly with Harford County DILP before budgeting or filing. The DILP Fee Schedule (Bill 24-013) is effective January 1, 2025 with a 01/01/2026 revision. Call 410-638-3122 or use the online permits portal at harfordcountymd.gov/985/Permits to confirm the current fee, whether your shed needs a permit, and the setback, lot-coverage, and floodplain rules for your property.
Disclaimer: All fee information on PermitPrice is for informational purposes only and is not an official permit quotation. Actual permit fees are determined by Harford County DILP at the time of application. Whether a shed requires a permit, and its placement and zoning limits, are set by county code and can change without notice. Trade permit fees (electrical, plumbing) and shed purchase or construction costs are excluded from the figures on this page.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.